Agenda Item # 5



Columbus Consolidated Government



Council Meeting

07/12/2011



Agenda Report # 664



TO: Mayor and Council



SUBJECT: Hilton Avenue Drainage Improvements



INITIATED BY: Engineering Department







Recommendation: Approval is requested to authorize the execution of a change

order in the amount of $23,023.00 for drainage improvements at 3312 Hilton

Avenue, Columbus, GA.



Background: On December 7, 2010 Council by Resolution No. 436-10 authorized

the execution of mutual agreements, construction contracts, promises and

benefits and to accept an easement for drainage improvements at 3312 Hilton

Avenue in the amount not to exceed $500,000. The final estimated construction

cost was not fully developed at the time of Council approval. The construction

was done under the City's annual contract Remediation and Disposal of

Environmental Hazardous Chemical Waste on as needed basis.



Analysis: During the construction the contractor encountered some unexpected

conditions due to the age of the property such as unsuitable soils, additional

pipes and utilities, additional curb and gutter and asphalt to tie in

driveways, etc.



Financial Considerations: Funding for the additional work required as part of

the project is available in the Drainage Project 21108.



Projected Annual Fiscal Impact Statement: Maintenance for the drainage

improvements on Hilton Avenue will be included in the general maintenance

responsibilities of the Rainwater Maintenance Division of Public Services.



Legal Considerations: Since the construction cost exceeded the $500,000

approved by Council in Resolution No. 436-10, Council authorization is needed

for final payment.



Recommendations/ Actions: Approve a resolution authorizing payment of

$23,023.00 to Kam, Inc. for additional cost incurred during the construction

of drainage improvements at 3312 Hilton Avenue.





















A RESOLUTION

NO. _____

A RESOLUTION AUTHORIZING THE EXECUTION OF A CHANGE ORDER IN THE AMOUNT OF

$23,023.00 TO KAM, INC. FOR DRAINAGE IMPROVEMENTS AT 3312 HILTON AVENUE,

COLUMBUS, GA.

WHEREAS, on December 7, 2010, Council approved Resolution No.436-10 for

agreements, easements and construction contracts up to $500,000 for the

construction of drainage improvements at 3312 Hilton Avenue; and,

WHEREAS, during construction the contractor encountered some unexpected site

conditions such as unsuitable soils, additional pipes and utilities, and

additional asphalt and curb and gutter requirements to tie in driveways. All

were related to the age of the property.

NOW, THEREFORE, THE COUNCIL OF COLUMBUS, GEORGIA, HEREBY RESOLVES AS FOLLOWS:

That the City Manager is hereby authorized to execute a change order

for additional work required as part of the construction of drainage

improvements at 3312 Hilton Avenue with KAM, Inc. in the amount of $23,023.000.

Funding is available in the Drainage Project 21108.

___________

Introduced at a regular meeting of the Council of Columbus, Georgia, held

the _________day of _____________, 2011 and adopted at said meeting by the

affirmative vote of

_____members of said Council.



Councilor Allen voting __________.







Councilor Henderson voting __________.

Councilor Huff voting __________.

Councilor McDaniel voting __________.

Councilor Turner Pugh voting __________.



Councilor Woodson voting __________.





_________________________ _________________________

Tiny Washington, Clerk of Council , Mayor