Agenda Item # 5 
       Columbus Consolidated Government       
 Council Meeting   
 07/12/2011       
 Agenda Report # 664       
 TO:	  Mayor and Council       
 SUBJECT:	 Hilton Avenue Drainage Improvements       
 INITIATED BY: Engineering Department                
 Recommendation:  Approval is requested to authorize the execution of a change    
 order in the amount of $23,023.00 for drainage improvements at 3312 Hilton    
 Avenue, Columbus, GA.       
 Background:  On December 7, 2010 Council  by Resolution No. 436-10 authorized    
 the execution of mutual agreements, construction contracts, promises and    
 benefits and to accept an easement for drainage improvements at 3312 Hilton    
 Avenue in the amount not to exceed $500,000.  The final estimated construction    
 cost was not fully developed at the time of Council approval.  The construction    
 was done under the City's annual contract Remediation and Disposal of    
 Environmental Hazardous Chemical Waste on as needed basis.       
 Analysis:  During the construction the contractor encountered some unexpected    
 conditions due to the age of the property such as unsuitable soils, additional    
 pipes and utilities, additional curb and gutter and asphalt to tie in    
 driveways, etc. 	       
 Financial Considerations:  Funding for the additional work required as part of    
 the project is available in the Drainage Project 21108.       
 Projected Annual Fiscal Impact Statement:  Maintenance for the drainage    
 improvements on Hilton Avenue will be included in the general maintenance    
 responsibilities of the Rainwater Maintenance Division of Public Services.       
 Legal Considerations:  Since the construction cost exceeded the $500,000    
 approved by Council in Resolution No. 436-10,  Council authorization is needed    
 for final payment.        
 Recommendations/ Actions:  Approve a resolution authorizing payment of    
 $23,023.00  to Kam, Inc. for additional cost incurred during the construction    
 of drainage improvements at 3312 Hilton Avenue.                                           
  A RESOLUTION   
  NO.  _____   
 A RESOLUTION AUTHORIZING THE EXECUTION OF A CHANGE ORDER IN THE AMOUNT OF    
 $23,023.00 TO KAM, INC. FOR DRAINAGE IMPROVEMENTS AT 3312 HILTON AVENUE,    
 COLUMBUS, GA.   
 WHEREAS, on December 7, 2010, Council approved Resolution No.436-10 for    
 agreements, easements and construction contracts up to $500,000 for the    
 construction of drainage improvements at 3312 Hilton Avenue; and,   
 WHEREAS, during construction the contractor encountered some unexpected site    
 conditions such as unsuitable soils, additional pipes and utilities, and    
 additional asphalt and curb and gutter requirements to tie in driveways.  All    
 were related to the age of the property.   
 NOW, THEREFORE, THE COUNCIL OF COLUMBUS, GEORGIA, HEREBY RESOLVES AS FOLLOWS:    
 	That the City Manager is hereby authorized to execute a change order    
 for additional work required as part of the construction of drainage    
 improvements at 3312 Hilton Avenue with KAM, Inc. in the amount of $23,023.000.    
 Funding is available in the Drainage Project 21108.    
 ___________   
    Introduced at a regular meeting of the Council of Columbus, Georgia, held    
 the _________day of _____________, 2011 and adopted at said meeting by the    
 affirmative vote of    
 _____members of said Council.       
 Councilor Allen voting                               __________.               
 Councilor Henderson voting                      __________.   
 Councilor Huff voting                                __________.   
 Councilor McDaniel voting                        __________.   
 Councilor Turner Pugh voting                    __________.       
 Councilor Woodson voting                        __________.           
 _________________________                      _________________________   
 Tiny Washington, Clerk of Council                          , Mayor             
        
Attachments