Agenda Item # 3
Columbus Consolidated Government
Council Meeting
04/26/2016
Agenda Report # 113
TO: Mayor and Council
SUBJECT: TIA Supplement Agreement No. 2 - US27/Custer Road
Interchange Reconstruction/Modification
INITIATED BY: Planning Department
Recommendation: Approval is requested to enter into a supplemental agreement
with the Georgia Department of Transportation to adjust the budget for the
Transportation Improvement Act Project, that will provide necessary funding for
engineering consulting services.
Background: The US27/Custer Road Interchange Reconstruction/Modification is a
Transportation Investment Act (TIA) project that was approved by voters in July
2012. The project will provide direct access to property located at the
intersection of US 27 (Victory Drive) and I-185 for the purposes of developing
a business park.
Analysis: A supplemental agreement is needed to modify the existing budget for
the above referenced project. Line items in the original contract for ROW and
construction have been reduced by a total of $700,000, with that amount being
applied to the line item for preliminary engineering.
Financial Considerations: The total amount of $20 million in TIA funds for
this project has not changed. This action will allow us to maintain our
contractural obligations with the consultants on this project.
Projected Annual Fiscal Impact Statement: There will not be any annual fiscal
impact to the city for this action.
Legal Considerations: The City Attorney has approved this action.
Recommendations/Actions: Approval is requested to enter into a supplemental
agreement with the Georgia Department of Transportation to adjust the budget
for the Transportation Improvement Act Project, that will provide necessary
funding for engineering consulting services.
A RESOLUTION
No._____
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER INTO SUPPLEMENTAL AGREEMENT
NUMBER 2 WITH THE GEORGIA DEPARTMENT OF TRANSPORTATION TO ADJUST THE BUDGET FOR
THE TRANSPORTATION IMPROVEMENT ACT PROJECT U.S. 27/CUSTER ROAD INTERCHANGE
RECONSTRUCTION/MODIFICATION.
WHEREAS, the U.S. 27/Custer Road Interchange Reconstruction/Modification is a
$20,000,000 Transportation Improvement Act project that was approved by the
voters on July 30, 2012; and,
WHEREAS, a supplemental agreement with the Georgia Department of Transportation
is needed to allow for an adjustment of funds for engineering of the project;
and,
WHEREAS, the adjustment of these funds will not affect the total budget for
this project.
NOW, THEREFORE, THE COUNCIL OF COLUMBUS, GEORGIA, HEREBY RESOLVES AS FOLLOWS:
That the City Manager is hereby authorized to enter into Supplemental
Agreement Number 2 with the Georgia Department of Transportation to adjust the
budget for this project to provide the necessary funding for engineering
consulting services.
____________________
Introduced at a regular meeting of the Council of Columbus, Georgia, held the
_________ day of _____________, 2016 and adopted at said meeting by the
affirmative vote of _____________ members of said Council.
Councilor Allen voting __________.
Councilor Baker voting __________.
Councilor Barnes voting __________.
Councilor Buck voting __________.
Councilor Davis voting __________.
Councilor Henderson voting __________.
Councilor Huff voting __________.
Councilor Turner Pugh voting __________.
Councilor Thomas voting __________.
Councilor Woodson voting __________.
______________________________ _________________________
Tiny B. Washington, Clerk of Council , Mayor