I-185 RESURFACING PROJECT
STATUS REPORT
________________________
The I-185 Re-surfacing project will begin after Labor Day and will be finished
in April 2009. It is a 41 mile project, going from Airport Blvd. to I-85 to
include on/off ramps. The cost of the project is $75,526,026.97. It will be a
24/7 work schedule outside of the populated area (Williams Rd or Smith Rd).
Restricted hours for the populated area.