Agenda Item # 1



Columbus Consolidated Government



Council Meeting

03/13/2012



Agenda Report # 021



TO: Mayor and Council



SUBJECT: Whittlesey Rd project #: STP00-8060-00(002), Muscogee County

Railroad Force Account Agreement



INITIATED BY: Engineering







Recommendation: Approval is requested to execute a Three Party agreement

between the Georgia Department of Transportation, Central of Georgia Railroad

Company and the City for reconstruction of Whittlesey Road railroad crossing

and to run traffic signal interconnect across railroad right-of-way.



Background: The Georgia Department of Transportation (DOT) is finalizing

construction plans for the widening of Whittlesey Road. Since there is road

construction and a traffic signal interconnect (ATMS) cable crossing the

railroad right-of-way, a formal agreement is required between all three parties.



Analysis: The execution of this agreement is required to keep this project on

track for construction.



Financial Considerations: Both the ATMS cabling and the construction of the

new railroad crossing is ($127,455.00) to be funded by the DOT as part of this

project. The Traffic Engineering Division will be responsible for maintaining

the ATMS cabling as part of the traffic signal system.



Projected Annual Fiscal Impact Statement: Any future maintenance costs for the

ATMS cable will be incurred by the Traffic Engineering Division's budget.



Legal Considerations: All agreements require the City Council's approval.



Recommendations/ Actions: Authorize the execution of the Three Party agreement

between the City, Georgia Department of Transportation and Central of Georgia

Railroad Company for the Whittlesey Road widening project.















A RESOLUTION

NO. ____

A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE A THREE PARTY AGREEMENT

BETWEEN THE COLUMBUS CONSOLIDATED GOVERNMENT, THE GEORGIA DEPARTMENT OF

TRANSPORTATION AND THE CENTRAL OF GEORGIA RAILROAD COMPANY FOR UPGRADING THE

EXISTING RAILROAD CROSSING AND TO ALLOW AN ATMS CABLE FOR TRAFFIC SIGNALS TO

CROSS RAILROAD RIGHT-OF-WAY AS PART OF THE WHITTLESEY ROAD PROJECT #:

STP00-8060-00(002) MUSCOGEE COUNTY.

WHEREAS, this project upgrades the existing railroad grade crossing with

prefabricated crossing panels and provides for an ATMS cable for traffic signal

interconnect to cross railroad right-of-way; and,

WHEREAS, the maintenance of the ATMS cable will be the responsibility of the

Columbus Consolidated Government as part of their traffic signal systems; and,

WHEREAS, the Traffic Engineering Manager and the City Attorney reviewed said

agreement and are recommending approval.

NOW, THEREFORE, THE COUNCIL OF COLUMBUS, GEORGIA, HEREBY RESOLVES AS FOLLOWS:

THAT THE CITY MANAGER IS HEREBY AUTHORIZED TO EXECUTE A THREE PARTY AGREEMENT

BETWEEN THE COLUMBUS CONSOLIDATED GOVERNMENT, GEORGIA DEPARTMENT OF

TRANSPORTATION AND THE CENTRAL OF GEORGIA RAILROAD COMPANY FOR THE PURPOSE OF

UPGRADING THE EXISTING RAILROAD CROSSING AND TO ALLOW AN ATMS CABLE FOR TRAFFIC

SIGNALS TO CROSS RAILROAD RIGHT-OF-WAY AS PART OF THE WHITTLESEY ROAD PROJECT

#: STP00-8060-00(002) MUSCOGEE COUNTY.

___________

Introduced at a regular meeting of the Council of Columbus, Georgia, held

the _________day of _____________, 2012 and adopted at said meeting by the

affirmative vote of

_____________members of said Council.



Councilor Allen voting __________.







Councilor Henderson voting __________.

Councilor Huff voting __________.

Councilor McDaniel voting __________.

Councilor Turner Pugh voting __________.



Councilor Woodson voting __________.





_________________________________

_________________________

Sandra T. Davis, Deputy Clerk of Council , Mayor



Attachments


Back to List