David Arrington/Columbusga
09/26/2006 11:03 PM
To
Isaiah Hugley/Columbusga@Columbusga
cc
Donna Newman/Columbusga@Columbusga
Subject
Flood Abatement and Stormwater Rehab Projects
Isaiah,
In the absence of objections from Council this morning to either the 6th Avenue
Flood Abatement Project or the Stormwater Rehabilitation Project, we will
direct our consultant J.J. & G. to proceed with developing specifications for
both projects. I'll provide a projected timetable for the process as soon as
the consultant provides one.
We also provided Council information on additional work needed on Atterbury
Drive. Proceeding with the additional pipe repairs on Atterbury was also
included in our final recommendations for the stormwater rehab. project.
Since no objections were stated to the recommendations, I would like to have
our contractor proceed with repairing the pipe under our existing contract for
this project. The approximate amount of the repair is $100,000. We would
bring the expenditure back as a change order to the contract at a later date.