Columbus, Georgia

Georgia's First Consolidated Government

Post Office Box 1340
Columbus, Georgia, 31902-1340
(706) 653-4013
fax (706) 653-4016

Council Members

Agenda Item # 5





Columbus Consolidated Government

Council Meeting



02/14/17



Agenda Report # 91





TO: Mayor and Council



SUBJECT: Resurfacing and Restriping of Martin Luther King, Jr. Boulevard (MLK,

Jr. Boulevard)



INITIATED BY: Planning Department

_____________________________________________________________________________

Recommendation: Approval is requested to authorize the resurfacing, restriping,

of Martin Luther King, Jr. Boulevard, with the addition of a 12 foot multi-use

trail and intersection improvements at Brown Avenue and Martin Luther King, Jr.

Boulevard.



Background: Martin Luther King, Jr Boulevard runs between Buena Vista Road and

10th Avenue, consisting of two sections. Currently the section between Buena

Vista Road and Brown Avenue is four lanes, with a center turn lane, while the

section between Brown Avenue and 10th Avenue is four lanes only. The average

daily traffic for the entire length of this road totals no more than 7,700, far

below the projected carrying capacity of 22,200 for a roadway of this type.

This project would resurface the entire length of MLK, Jr. Boulevard, while

leaving intact the existing laneage in place. Additional road improvements

will include the construction of a 12 foot multi-use trail from Buena Vista

Road to 10th Avenue, plus signal and intersection improvements at MLK, Jr.

Boulevard and Brown Avenue.



Analysis: This is a road resurfacing project that is needed for this roadway.

The road will be restriped exactly as it is configured today, with five lanes

from Buena Vista Road to Brown Avenue, and four lanes from Brown Avenue to 10th

Avenue. The exception to this would be the reduction of one west bound lane

for approximately 2,300 linear feet from Magnolia Avenue to Davis Elementary

School. The purpose of this action is to accommodate the 12 foot wide multi-use

trail that will be constructed along the entire length of the north side of the

road. This reduction in this one lane is due to the lack of necessary right of

way needed for the trail for this portion of the roadway. In addition, an

upgrading of the signals at Brown Avenue and MLK, Jr. Boulevard would be

performed, along with landscaping and improvements to the pedestrian crossings.



Financial Considerations: Funding has been allocated in the amount of

$4,000,000 from the OLOST Infrastructure, Paving Fund, and TSPLOST

Discretionary funds.



Projected Annual Fiscal Impact Statement: Minimal maintenance is expected over

the ten year period upon completion of this project.



Legal Considerations: There are legal consideration at this time.



Recommendation/Action: Approval is requested to authorize the resurfacing,

restriping, of Martin Luther King, Jr. Boulevard, with the addition of a 12

foot multi-use trail and intersection improvements at Brown Avenue and Martin

Luther King, Jr. Boulevard.





A RESOLUTION

No. _______



A RESOLUTION AUTHORIZING THE RESURFACING AND RESTRIPING OF MARTIN LUTHER KING,

JR BOULEVARD



WHEREAS, Martin Luther King, Jr. Boulevard is a connector roadway consisting of

a five lane segment between Buena Vista Road and Brown Avenue, and a four lane

segment between Brown Avenue and 10th Avenue; and,



WHEREAS, this roadway is rated a 44 under the Department of Engineering?s

Paving Management, and is need of resurfacing; and,



WHEREAS, it has been determined that existing lane striping should remain for

this roadway; and,



WHEREAS, the PATH Foundation has proposed a 12 foot wide multi-use trail and

streetscapes that would be developed in conjunction with this project, that

requires a section of this roadway to be converted to three lanes; and,



WHEREAS, funding for this project to include resurfacing, restriping multi-use

trail, signal and intersection improvements, as well as the coordination of the

Martin Luther King, Jr. Learning Trail, has been budgeted from OLOST

Infrastructure, Paving Fund, and TSPLOST Discretionary Funds in the amount of

$4,000,000;



NOW, THEREFORE, THE COUNCIL OF COLUMBUS, GEORGIA HEREBY RESOLVES AS FOLLOWS:



That the City Manager is hereby authorized to direct the Department of

Engineering to resurface and restripe Martin Luther King, Jr. Boulevard, five

lanes beginning at Buena Vista Road to Brown Avenue, and four lanes beginning

at Brown Avenue to 10th Avenue. The City Manager is further authorized to

proceed forward with the proposed 12 foot wide multi-use trail as proposed by

the PATH Foundation, Inc. and signal/intersection improvements with the funding

available.

_____________



Introduced at a regular meeting of the Council of Columbus, Georgia held the

___14____ day of February 2017 and adopted at said meeting by the affirmative

vote of _______ members of said Council.





Councilor Allen voting __________.

Councilor Baker voting __________.

Councilor Barnes voting __________.

Councilor Davis voting __________.

Councilor Garrett voting __________.

Councilor Henderson voting __________.

Councilor Huff voting __________.

Councilor Thomas voting __________.

Councilor Turner Pugh voting __________.

Councilor Woodson voting __________.







_______________________________ _________________________

Tiny B. Washington, Clerk of Council Teresa Pike Tomlinson,

Mayor

Attachments