Agenda Item ________



COLUMBUS CONSOLIDATED GOVERNMENT



COUNCIL MEETING



September 23, 2014



Agenda Report #______________



TO: Mayor and Councilors



SUBJECT: Demolition of Derelict Buildings by City Contract



INITIATED BY: Development Resource Center - Inspections and Code



*********************************



Recommendation: Approve the demolition of nineteen (19) structures deemed

unsafe under the City?s building ordinance, as priced by D.H. Griffin Wrecking

Company, Inc. A chronology is attached for each structure.



Background: Upon routine investigation, Property Maintenance Inspectors

made inspections of the properties, took photographs and wrote up the

structures according to the unsafe building ordinance (Section 8-81 - 8-90 of

the Columbus Code of Ordinances). Inspections and Code notified the owners of

the hearings to be held, held hearings, and then mailed notices to the owners,

giving them 45 days in which to demolish or to repair the structures.



Analysis: The following structures have been written up in accordance with

the unsafe building ordinance and owners have received proper legal notice of

the proposed demolition: 2317 5th Ave, Montgomery, 1517 25th St, Mitchell,

2720 Baldwin St, Ameris Bank, 1331 Winshire St, Jordan, 3039 Morehouse St,

Walton, 2431 14th Ave., Watson, 2901 3rd Ave, Lentz, 6426 Buena Vista Rd,

Harris, 2414 14th Ave, Antioch Baptist Church of Columbus, 4961 Gardiner Dr,

Captive Investments, 3 Lafayette Dr, Gobbell, 333 27th St, Davis, 3331 8th St,

Peabody, 2927 Colorado St, Pitts, 947 34th Ave, Jordan, 2327 B 5th Ave,

Montgomery, 1417 25th St, Moore, 2325 Alford St, Gail, 2414 Courtland Ave,

Roberts.



The only alternative to the City?s proceeding with the demolition will be for

the owners to complete the demolition of the structures prior to approval by

Council and affirmative action by the demolition company.



Financial Considerations: Demolitions under City contracts are funded by the

Community Development Block Grant Program (CDBG) and the General Fund

(0101-240-2200-6381). The City has signed an annual contract with D.H. Griffin

Wrecking Company, Inc., to do all of the demolitions for the City. Upon

completion of the demolitions, the City will pay D.H. Griffin with funds from

CDBG and the General Fund and will file liens against the properties for the

cost of the demolitions. These liens will have to be repaid to the City before

the owners can sell the properties. The total estimated cost for this

demolition project is $114,155.50.



Legal Considerations: All precautions have been taken to assure that the

owners received proper notification of all actions by the City. The annual

contract between D.H. Griffin Wrecking Company, Inc., and the City outlines the

responsibility of Reaves in performing their work.



Recommendations/Actions: Approve the demolition of nineteen (19) structures

deemed unsafe under the City?s building ordinance, as priced by D.H. Griffin

Wrecking Company, Inc.





































Attachments


No attachments for this document.

Back to List