Subject Whittlesey Road Widening
Description Have the staff to provide a timeline as to when the right-of-way
purchases will begin for the Whittlesey Road widening project and when will we
be making contact with the residents.
(Request of Councilor Allen)
Received From
Assigned To Felton Grant, Donna Newman, Rick Jones, David Arrington
Please enter a date mm/dd/yy before any comments are added.
Response 02-02-06 -- Please see timeline below:
-- Right of Way plans should be in by March 06.
-- Appraisals three months after receiving Righ-of-Way Plans
--DOT has to review the appraisals which takes about three months after they
receive them.
-- We should start negotiations by Sept. 06.
-- Negotiations should take about 18 months for all parcels (65).