TO: Mayor and Councilors



SUBJECT: Road Improvement, Safety and Alternative Transportation

Projects



INITIATED BY: City Manager?s Office



Recommendation: Approval is requested to proceed with executing and funding the

pre-construction requirements for Road Improvement, Safety, and Alternative

Transportation Projects totaling $16,525,000 funded through the Other Local

Option Sales Tax (OLOST), Transportation Special Purpose Local Option Sales Tax

(TSPLOST) Discretionary Funds, State of Georgia, Department of Transportation

Local Maintenance and Improvement Grants (LMIG) and M230 funds, and the Paving

Fund to include right of way acquisition, permanent and temporary construction

easements, utility relocation, environmental mitigation and other necessary

agreements to prepare projects for construction.



Background: The following list of road improvement, safety and alternative

transportation projects have been identified, budget estimates provided, and

funded through the OLOST, TSPLOST Discretionary, Paving Fund or GDOT LMIG and

M230:

Victory Drive/30th Avenue Signal (LMIG) - $150,000

Ada Avenue/Wynnton Road Signal (LMIG) - $250,000

Forrest Road Phase I Additional Funding (Paving Fund) - $1,500,000

Reese Road Bridge at Cooper Creek (Paving Fund/TSPLOST Discretionary) -

$2,500,000

Claradon Bridge (TSPLOST Discretionary) - $300,000

Sidewalks/ADA (TSPLOST Discretionary) - $100,000

Traffic Calming (TSPLOST Discretionary) - $100,000

Guardrails (TSPLOST Discretionary) -$100,000

Steam Mill Road Sidewalk Concept (OLOST) - $200,000

Follow Me Trail Bridge (Paving Fund) - $1,500,000

Martin Luther King Jr. Streetscapes and Trail (TSPLOST Discretionary/Paving

Fund) ?$3,000,000 (Design to be approved by council)

Infantry Road and Trail (GDOT M230) - $1,500,000

10th Street Plaza/Entrance to Riverwalk (GDOT M230) - $1,300,000

Mott?s Green Renovation (GDOT M230) - $1,000,000

Flat Rock/Beaver Run Traffic Software (GDOT M230) - $125,000

Wynnton Road Streetscapes (Paving Fund) - $400,000

Resurfacing (Paving Fund/OLOST) - $2,300,000

Park ADA Upgrades (OLOST) - $100,000

Fiber Interconnect (TSPLOST Discretionary) - $100,000



Analysis: The completion of the pre-construction activities for road

improvements, safety, and alternative transportation projects is required prior

to the project being authorized for competitive bids.



Financial Considerations: Funding for said projects will be funded with the

OLOST, TSPLOST Discretionary, or GDOT LMIG and M230.



Legal Considerations: The City Attorney approves this resolution.



Recommendations/Actions: Approve a resolution authorizing the City Manager to

proceed with executing and funding the pre-construction requirements for Road

Improvement, Safety, and Alternative Transportation Projects totaling

$16,525,000 funded through the Other Local Option Sales Tax (OLOST),

Transportation Special Purpose Local Option Sales Tax (TSPLOST) Discretionary

Funds, State of Georgia, Department of Transportation Local Maintenance and

Improvement Grants (LMIG) and M230 funds, and the Paving Fund to include right

of way acquisition, permanent and temporary construction easements, utility

relocation, environmental mitigation and other necessary agreements to prepare

projects for construction.



A RESOLUTION

No. ________



A RESOLUTION AUTHORIZING THE CITY MANAGER TO PROCEED WITH EXECUTING AND FUNDING

THE PRE-CONSTRUCTION REQUIREMENTS FOR ROAD IMPROVEMENT, SAFETY, AND ALTERNATIVE

TRANSPORTATION PROJECTS TOTALING $16,525,000 FUNDED THROUGH THE OTHER LOCAL

OPTION SALES TAX (OLOST), TRANSPORTATION SPECIAL PURPOSE LOCAL OPTION SALES TAX

(TSPLOST) DISCRETIONARY FUNDS, OR STATE OF GEORGIA, DEPARTMENT OF

TRANSPORTATION LOCAL MAINTENANCE AND IMPROVEMENT GRANTS (LMIG) AND M230, AND

PAVING FUND TO INCLUDE RIGHT OF WAY ACQUISITION, PERMANENT AND TEMPORARY

CONSTRUCTION EASEMENTS, UTILITY RELOCATION, ENVIRONMENTAL MITIGATION AND OTHER

NECESSARY AGREEMENTS TO PREPARE THE PROJECTS FOR CONSTRUCTION.



WHEREAS, the completion of pre-construction activities for road improvement

projects is required prior to the project being authorized for competitive bid;

and,



WHEREAS, these activities include buy not limited to right of way acquisition,

permanent and temporary construction easements, utility relocation, and

environmental mitigation; and



WHEREAS, the following list of road improvement, safety and alternative

transportation projects have been identified, budget estimates provided, and

funded through OLOST, TSPLOST Discretionary, GDOT LMIG and M230 funds, and the

Paving Fund,

Victory Drive/30th Avenue Signal (LMIG) - $150,000

Ada Avenue/Wynnton Road Signal (LMIG) - $250,000

Forrest Road Phase I Additional Funding (Paving Fund) - $1,500,000

Reese Road Bridge at Cooper Creek (Paving Fund/TSPLOST Discretionary) -

$2,500,000

Claradon Bridge (TSPLOST Discretionary) - $300,000

Sidewalks/ADA (TSPLOST Discretionary) - $100,000

Traffic Calming (TSPLOST Discretionary) - $100,000

Guardrails (TSPLOST Discretionary) -$100,000

Steam Mill Road Sidewalk Concept (OLOST) - $200,000

Follow Me Trail Bridge (Paving Fund) - $1,500,000

Martin Luther King Jr. Streetscapes and Trail (TSPLOST Discretionary/Paving

Fund) ?$3,000,000 (Design to be approved by council)

Infantry Road and Trail (GDOT M230) - $1,500,000

10th Street Plaza/Entrance to Riverwalk (GDOT M230) - $1,300,000

Mott?s Green Renovation (GDOT M230) - $1,000,000

Flat Rock/Beaver Run Traffic Software (GDOT M230) - $125,000

Wynnton Road Streetscapes (Paving Fund) - $400,000

Resurfacing (Paving Fund/OLOST) - $2,300,000

Park ADA Upgrades (OLOST) - $100,000

Fiber Interconnect (TSPLOST Discretionary) - $100,000





WHEREAS, funding for pre-construction and construction services for the above

projects is available through the OLOST, SPLOST, TSPLOST Discretionary, LMIG

and M230, and the Paving Fund.



NOW, THEREFORE, THE COUNCIL OF COLUMBUS, GEORGIA HEREBY RESOLVES:



The City Manager is hereby authorized to proceed with the executing and funding

the pre-construction requirements for the road improvement, safety and

alternative transportation projects totaling $16,525,000 funded through OLOST,

TSPLOST Discretionary, LMIG, M230 and Paving Fund as identified above to

include right of way acquisition, permanent and temporary construction

easements, utility relocation, environmental mitigation and other necessary

agreements to prepare the projects for construction.



______________

Introduced at a regular meeting of the Council of Columbus, Georgia,

held the _________ day of _____________ 2016, and adopted at said meeting by

the affirmative vote of ________ members of said Council.





Councilor Allen voting __________.

Councilor Baker voting __________.

Councilor Barnes voting __________.

Councilor Davis voting __________.

Councilor Garrett voting __________.

Councilor Henderson voting __________.

Councilor Huff voting __________.

Councilor Thomas voting __________.

Councilor Turner Pugh voting __________.

Councilor Woodson voting __________.







_______________________________ __________________________

Tiny B. Washington, Clerk of Council Teresa Pike Tomlinson, Mayor

Attachments


No attachments for this document.

Back to List