AN ORDINANCE
NO.
An ordinance amending the Unified Development Ordinance (UDO) for Columbus,
Georgia so as to amend certain sections of the Unified Development Ordinance of
Columbus, Georgia so as to alter Chapter 10 Article 8 and Chapter 8 Article 9.
---------------
THE COUNCIL OF COLUMBUS, GEORGIA HEREBY ORDAINS:
Section 1.
Chapter 10 of the Unified Development Ordinance is hereby amended by repealing
Article 8 in its entirety and replacing it with a new Article 8 to read as
follows:
?Article 8. Building Permitting
Section 10.8.1 Procedure to Obtain a Building Permit.
Refer to Section 8-14.4 of the Columbus Code for Building Permit Requirements
and Fees.?
SECTION 2.
Chapter 8 of the Unified Development Ordinance is hereby amended by repealing
Section 8.9.1.A and replacing it with a new Section 8.9.1.A to read as follows:
?A. Issuance of Permits. When required, building permits shall be issued in
conformance with the technical codes adopted and amended by the City under the
Georgia uniform Codes Act. Refer to Sec. 8-14.4 of the Columbus Code for
Building Permit Requirements and Fees.?
SECTION 3.
Chapter 8 of the Unified Development Ordinance is hereby amended by inserting
new Sections 8.9.1.G and 8.9.1.H to read as follows:
?G. Zoning verification. Prior to issuance of a building permit, a verification
shall be obtained. The following information shall be reviewed prior to this
action.
1. Single family or two-family ?Duplex? Dwellings. For a single family
detached or two-family dwelling, a plat of the lot showing the outline of the
principal building and minimum building setback lines for the lot.
2. Multi-family or nonresidential Buildings. For a multi-family or
nonresidential building, the site plan upon which was granted project approval
by the director of Inspections and Code.
3. Street Address. A street address number as assigned by the geographic
Information System Division (GIS).
H. Simultaneous Application and Review. An application for a building permit
may proceed simultaneously with and application for project approval of a site
plan, but the permit may not be issued prior to project approval of such site
plan by the Engineering Department.?
SECTION 4.
All ordinances or parts of ordinances in conflict with this ordinance are
hereby repealed.
---------------
Introduced at a regular meeting of the Council of Columbus, Georgia held on the
25th day of April, 2017 introduced a second time at a regular meeting of said
Council held on the ______ day of ________, 2017, and adopted at said meeting
by the affirmative vote of ________ members of said Council.
Councilor Allen voting____________.
Councilor Baker voting____________.
Councilor Barnes voting____________.
Councilor Davis voting____________.
Councilor Garrett voting____________.
Councilor Henderson voting____________.
Councilor Huff voting____________.
Councilor Pugh voting____________.
Councilor Thomas voting____________.
Councilor Woodson voting____________.
______________________________ ______________________________
TINY B. WASHINGTON TERESA PIKE TOMLINSON
CLERK OF COUNCIL MAYOR
Attachments
No attachments for this document.