Subject: Signal Installation Schedule
No attachments for this document.
Find listed below the schedule for installations or improvements to intersections:
Location Projected Completion
Veterans Pkwy @ South Ramps, J. R. Allen Pkwy August 02
Moon Road @ North/South Ramps @ J. R. Allen Pkwy August 02
Moon Road @ Livingston Drive August 02
Veterans Pkwy @ Moon Road April 02
River Road @ 54th Street July 02
River Road @ Mobley Road July 02
Whitesville Road @ Lyons Drive TBD
All of the above completion dates are dependent on approval and requirements of the Georgia Department of Transportation (DOT) with the exception of Moon Road @ Livingston Drive and Whitesville Road @ Lyons Drive. City Staff has provided all the necessary information to DOT.
Based on Council direction on Tuesday's January 29th, Staff has contacted the developer and is proceeding with the installation of the signal at Whitesville Road @ Lyons Drive.