Norfolk Southern Railroad will be doing work on the following crossings during

the next few weeks. The location and dates are listed below. The work at each

location should take less than a day. The railroad is responsible for traffic

control.

Forest Road will be done in two phases. The first phase will be Sunday

November 10, 2002.

Midland Rd. November 18

Pope Rd. November 19

Garrett Rd. November 21

Lynch Rd. November 25

Chattsworth Rd. November 27

Schatulga Rd. December 2

Cargo Dr. December 3

Woodruff Farm December 3

Forest Rd. December 9

Lamore St. December 9

Morris Rd. December 10

If you have any questions please contact me.