COLUMBUS CONSOLIDATED GOVERNMENT
COUNCIL MEETING
May 11, 2004
Agenda Report #______________
TO: Mayor and Councilors
SUBJECT: Bids for Demolition of Derelict Buildings by City Contract
INITIATED BY: Department of Economic and Community Development
*********************************
Recommendation: Approve the cost of the demolition of nine structures, as
priced by Reaves
Wrecking Company, Inc. A Status Report and Chronology is attached for each
structure.
Background: Upon routine investigation, Housing Code Inspectors made
inspections of the properties, took photographs and wrote up the structures
according to the unsafe building ordinance (Section 8-81 - 8-90 of the Columbus
Code of Ordinances). Inspections and Code Enforcement Division notified the
owners of the hearings, held hearings, and then mailed notices to the owners,
giving them 45 days in which to demolish or to repair the structures.
Analysis: No progress has been made on the following: 629 Lawyers Lane,
Daniel, 4247 Earline Avenue, Langley, 3466 Marathon Drive, Lots 44, 45, 51, &
62, Nelms, 18 Lafayette Drive, Thomas, Some progress was made on the
following: 3220 River Avenue, Vista Del Bibb and 3221 Park Avenue, Vista Del
Bibb.
Alternatives: The only alternative to the City?s proceeding with the
demolition will be for the owners to complete the demolition of the structures
prior to approval by Council.
Financial Considerations: Demolitions under City contracts are funded by the
Community Development Block Grant Program (CDBG). The City has signed an
annual contract with Reaves Wrecking Company, Inc., to do all of the
demolitions for the City. Upon completion of the demolitions, the City will
pay Reaves with funds from CDBG and will file liens against the properties for
the cost of the demolitions. These liens will have to be repaid to the City
before the owners can sell the properties.
Legal Considerations: All precautions have been taken to assure that the
owners received proper notification of all actions by the City. The annual
contract between Reaves Wrecking Company, Inc., and the City outlines the
responsibility of Reaves in performing their work.
Recommendations/Actions: Approve the costs, as priced by Reaves, for the
demolition of the structures and the clearing of the lots of the debris.
WLDJr:jsd
STATUS & CHRONOLOY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: DANIEL, Katie Shepherd & George
ADDRESS: 629 Lawyers Lane
DATE: May 4, 2004
I: LOCATION: Tax Map 40, Block 5, Lot 5
II: BUILDING CONDITION AND CURRENT STATUS
At the time original inspection was made, structure was neglected
and rotten. Owner has done nothing either to repair or demolish.
III: CHRONOLGY
11-7-03 Housing Code Inspector inspected the property, and found the
structure to be neglected and rotten, made photographs of the property and
wrote up "Inspector's Condemnation Report".
1-14-04 Notice of hearing to be held mailed to owner of record.
1-28-04 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed
to owner.
2-6-04 Ran legal ad.
3-12-04 Inspections revealed that no progress has been made.
3-18-04 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council
for approval of demolition.
3-18-04 Requested asbestos survey from GLE Associates.
4-16-04 Received asbestos survey from GLE Associates.
4-23-04 Haley Carpenter, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $3,508.75 and GLE Associates priced the cost
of asbestos survey at $332.00 totaling $3,840.75.
CHRONOLOGY
Page 2
May 4, 2004
4-28-04 Re-inspections and new photographs revealed that no progress has
been made.
4-30-04 Letter mailed to owner advising cost of demolition and Council
dates.
5-11-04 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: LANGLEY, Steven L.
ADDRESS: 4247 Earline Avenue
DATE: May 4, 2004
I: LOCATION: Tax Map 31, Block 19, Lot 2A
II: BUILDING CONDITION AND CURRENT STATUS
At the time original inspection was made, property was fire
damaged. Owner has done nothing either to repair or demolish.
III: CHRONOLOGY
7-29-03 Housing Code Inspector inspected the property, and found the
structure to be fire damaged, made photographs of the property, and wrote up
"Inspector's Condemnation Report".
9-10-3 Notice of hearing to be held mailed to owner of record.
9-24-03 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed
to owner.
11-5-03 Property sold.
1-14-04 Notice of hearing to be held mailed to new owner.
1-27-04 Owner bought permits to repair.
1-28-04 Hearing held. Forty-five day "Notice to Repair of Demolish" mailed
to owner.
3-12-04 Inspections revealed that no progress has been made.
3-18-04 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council
for approval of demolition.
3-18-04 Requested asbestos survey from GLE Associates.
4-16-04 Received asbestos survey from GLE Associates.
CHRONOLOGY
Page 2
May 4, 2004
4-23-04 Haley Carpenter, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $2,745.00 and GLE Associates priced the cost
of asbestos survey at $325.00 totaling $3,070.00,
4-28-04 Re-inspections and new photographs revealed that no progress has
been made.
4-30-04 Letter mailed to owner advising cost of demolition and Council
dates.
5-11-04 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: NELMS, Mamie
ADDRESS: 3466 Marathon Drive, Lots 44, 45, 51 and 62
DATE: May 4, 2004
I: LOCATION: Tax Map 63, Block 40, Lot 4
II: BUILDING CONDITION AND CURRENT STATUS
At the time original inspection was made, structures were neglected
and vandalized. Owner has done nothing either to repair or demolish.
III: CHRONOLOGY
6-27-03 Housing Code Inspector inspected the property, and found the
structures to be vandalized and neglected, made photographs of the
property, and wrote up "Inspector's Condemnation Report".
8-13-03 Notice of hearing to be held mailed to owner of record.
8-27-03 Hearing held. Forty-five day "Notice to Repair or Demolish" hand
delivered to owner.
10-15-03 Inspections revealed that no progress has been made.
1-13-04 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council
for approval of demolition.
1-13-04 Requested asbestos survey from GLE Associates.
1-30-04 Owner bought demo permits.
2-12-04 Received asbestos survey from GLE Associates.
3-1-04 Re-inspections revealed that no progress has been made.
4-23-04 Haley Carpenter, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $9,656.70 and GLE Associates priced the cost
of asbestos survey at $1,300.00, totaling $10,95670.
CHRONOLOGY
Page 2
May 4, 2004
4-28-04 Re-inspections and new photographs revealed that no progress has
been made.
4-30-04 Letter mailed to owner advising cost of demolition and Council
dates.
5-11-04 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: THOMAS, Sethira Bell
ADDRESS: 18 Lafayette Drive
DATE: May 4, 2004
I: LOCATION: Tax Map 62, Block 64, Block 3
II: BUILDING CONDITION AND CURRENT STATUS
At the time original inspection was made, structure was neglected.
Owner has done nothing either to repair or demolish.
III: CHRONOLOGY
12-5-03 Housing Code Inspector inspected the property, and found the
structure to be neglected, made photographs of the property, and wrote up
"Inspector's Condemnation Report".
1-14-03 Notice of hearing to be held mailed to owner of record.
1-28-04 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed
to owner.
2-6-04 Ran legal ad.
3-12-04 Inspections revealed that no progress has been made.
3-18-04 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council
for approval of demolition.
3-18-04 Requested asbestos survey from GLE Associates.
4-16-04 Received asbestos survey from GLE Associates.
4-23-04 Haley Carpenter, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $4,655.00 GLE Associates priced the cost of
asbestos survey at $360.00 totaling $5,015.00.
4-28-04 Re-inspections and new photographs revealed that no progress has
been made.
CHRONOLOGY
Page 2
May 4, 2004
4-30-04 Letter mailed to owner advising cost of demolition and Council
dates.
5-11-04 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: VISTA DEL BILL, LLC
ADDRESS: 3220 River Avenue
DATE: May 4, 2004
I: LOCATION: Tax Map 9, Block 15, Lot 6
II: BUILDING CONDITION AND CURRENT STATUS
At the time original inspection was made, structure was fire
damaged. Owner has done nothing either to repair or demolish.
III: CHRONOLOGY
9-2-03 Housing Code Inspector inspected the property, and found the
structure to be fire damaged, made photographs of the property, and wrote up
"Inspector's Condemnation Report".
10-8-03 Notice of hearing to be held mailed to owner of record.
10-22-03 Hearing held. Forty-five day "Notice to Repair or Demolish" hand
delivered to owner.
12-11-03 Inspections revealed that no progress has been made.
2-5-04 Owner bought permit to repair.
3-18-04 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council
for approval of demolition.
3-18-04 Requested asbestos survey from GLE Associates.
4-16-04 Received asbestos survey from GLE Associates.
4-22-04 Framing inspection called for, not ready.
4-23-04 Haley Carpenter, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $5,910.90 and GLE Associates priced the cost
of asbestos survey at $332.00 totaling $6,242.90.
CHRONOLOGY
Page 2
May 4, 2004
4-28-04 Re-inspections and new photographs revealed that no progress has
been made.
4-30-04 Letter mailed to owner advising demolition costs and Council dates.
5-11-04 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: VISTA DEL BILL, LLC
ADDRESS: 3221 Park Avenue
DATE: May 4, 2004
I: LOCATION: Tax Map 9, Bock 15, lot 14
II: BUILDING CONDITION AND CURRENT STATUS
At the time original inspection was made, structure was neglected.
Owner has done nothing either to repair or demolish.
III: CHRONOLOGY
6-5-03 Housing Code Inspector inspected the structure, and found the
property to be neglected, made photographs of the property, and wrote up
"Inspector's Condemnation Report".
8-13-03 Notice of hearing to be held mailed to owner of record.
8-27-03 Hearing held. Forty-five day "Notice to Repair or Demolish" hand
delivered to owner.
10-14-03 Inspections revealed that some progress had been made, then ceased.
2-5-04 Owner bought permit to repair front porch and vinyl siding.
3-18-04 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council
for approval of demolition.
3-18-04 Requested asbestos survey from GLE Associates.
4-16-04 Received asbestos survey from GLE Associates.
4-23-04 Haley Carpenter, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $11,757.40 and GLE Associates priced the cost
of asbestos survey at $510.00 totaling $12,267.40.
4-23-04 Inspection called for, not ready.
CHRONOLOGY
Page 2
May 4, 2004
4-28-04 Re-inspections and new photographs revealed that no progress has
been made.
4-30-04 Letter mailed to owner advising cost of demolition and Council
dates.
5-11-04 Ordinance providing for demolition goes to Council for first reading.