Columbus, Georgia
Georgia's First Consolidated Government
Post Office Box 1340
Columbus, Georgia, 31902-1340
(706) 653-4013
fax (706) 653-4016
Council Members
STREETSCAPES PROJECT ON BROADWAY
CONSTRUCTION STATUS
Friday, September 23, 2005
The streetscapes construction work on Broadway continues in three separate
areas in order to try to accelerate current schedule. The three areas include
the 1200 Block of Broadway, 12th Street between Broadway and Front Avenue, and
half of the 1100 Block of Broadway.
1200 Block of Broadway:
This block is approximately eighty-five percent complete. All vehicle and
pedestrian traffic avenues are open. The final work area consists of grassing
the median and completing the fountain at midblock in the median. The schedule
calls for this block to be substantially complete by the end of October.
12th Street Construction Site:
The work from Broadway to Front Street on 12th Street is approximately
seventy-five percent complete. Major delays in work were contributed to
architect revising plans for the South side of the street due to the discovery
of large underground vaults belonging to the Ledger and located between the
building and the street thus preventing the construction of planned sidewalk
planters. There were also major conflicts with underground utilities during
installation of storm sewer laterals thus requiring design changes. The
schedule calls for this street to be substantially complete by the end of
October. The entire street should be open to traffic prior to this time.
1100 Block of Broadway:
The contractor is working half of this block at one time in order to try to
accelerate the schedule thru increased production. This will probably be the
only opportunity to try to construct half of a block at one time since an
increase of businesses will be encountered in the forthcoming areas. Major
utility conflicts have slowed the progress of work in this area. The primary
issues have been resolved and now work should progress more on schedule. Half
of the area should be open to vehicular traffic by the end of October and the
entire area should be open by Thanksgiving, if not sooner. Eighty to Ninety
percent of all construction work in this area should be complete by
Thanksgiving, the start of the Christmas season.
Two possibilities for continuing construction work during the Christmas
season. One is to stop work on Broadway and move the contractor to 11th Street
between Broadway and Front Avenue and construct the improvements in this area.
This action would increase the cost of the project due to scheduling delays
thus increasing general condition cost to the contractor. The other
possibility is to proceed on Broadway, working on the west side of Broadway
between the midblock of the 1100 Block and 11th Street. Vehicle traffic in this
area would be prohibited, however, pedestrian traffic could be maintained.
With no stoppage of work on Broadway, it is anticipated that the contractor
would begin the 1000 Block of Broadway during the month of March, 06'. If work
is stopped and moved to 11th Street, then work on the 1000 Block would be
delayed one to two months.
The anticipated completion of the entire project is sometime during the
beginning of the fourth quarter of 06' barring any further delays.