REQUESTED ASBESTOS SURVEY - APRIL 26, 2004



INSP. REF # OWNER LOCATION



112 04-0104 JONES, Jewel Lee & 719 Church Avenue

ROSS, Cynthia (House Only)

609 Griffin Street 3840 $6,173.25

Bainbridge, GA 39818



112 04-0192 MADISON, William J. & Shirley 2 Regatta Court (Apt Bldg)

04-0191 974 Overlook Drive 4213 Alpine Drive (Apt Bdg)

Columbus, GA 31906 3878 $32,556.00



112 04-0107 MICKLE, Charlie & Ora Lee 2827 Bradley Circle

2837 Bradley Circle (House Only)

Columbus, GA 31904 3885 $5,321.00



112 04-0108 MILLER, Worthy 4218 Willis Street

1621 Buford Avenue (House Only)

Columbus, GA 31903 3888 $3,314.00



112 04-0119 ROBINSON, Vera M. 820 Coolidge Avenue

2228 8th Street (House Only)

Columbus, GA 31906 3908 $2,353.25



112 04-0110 SHYTLE, James Ray 1637 Elvan Avenue

1637 Elvan Avenue (House Only)

Columbus, GA 31903 3915 $6,062.50



cc: Bank One

201 N. Central Avenue Fl 12

Phoenix, AZ 85004

Certified Mail #3918



112 04-0115 SPELLMAN-HUNG CAPITAL LLC 400 29th Ave, Lts 54 & 57

1415 Dartmouth Road (2-Trailers)

Columbus, GA 31904 3922 $3,883.75



113 04-0121 THOMAS, Jason Wayne 920 Benning Drive

634 Lee Road 2017 (House Only)

Phenix City, AL 36870 3924 19,176.50









STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: JONES, Jewel & ROSS, Cynthia Fedd



ADDRESS: 719 Church Avenue



DATE: June 1, 2004



I: LOCATION Tax Map 50, Block 39, Lot 30



II: BUILDING CONDITION AND CURRENT STATUS



At the time original inspection was made, structure was neglected.

Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



9-9-03 Housing Code Inspector inspected the property during the Community

Improvement Program in the South Lawyers Lane area, and wrote up Housing Code

Notice.



12-30-03 Owner bought a repair permit, but made no repairs.



1-20-04 Housing Code Inspector inspected the property, and found the

structure to be neglected, lacking maintenance, made photographs of the

property, and wrote up "Inspector's Condemnation Report".



2-11-04 Notice of hearing to be held mailed to owner of record.



2-25-04 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed

to owner.



4-12-04 Inspections revealed that no progress has been made, owner has

purchased a building permit.



4-26-04 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for

approval of demolition.



4-26-04 Requested asbestos survey from GLE Associates.



5-19-04 Received asbestos survey from GLE Associates.



5-25-04 Haley Carpenter, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $5,813.25 and GLE Associates priced the cost of

asbestos survey at $360.00 totaling $6,173.25.



CHRONOLOGY

Page 2

June 1, 2004



5-27-04 Re-inspections and new photographs revealed that no progress has been

made.



5-28-04 Letter mailed to owner advising cost of demolition and Council dates.



6-8-04 Ordinance providing for demolition goes to Council for first reading.







STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: MADISON, William J. & Shirley



ADDRESS: 2 Regatta Court & 4213 Alpine Drive



DATE: June 1, 2004



I: LOCATION: Tax Map 63, Block 4, Lot 68

Tax Map 90, Block 1, Lot 5



II: BUILDING CONDITION AND CURRENT STATUS



At the time original inspection was made, structure was dilapidated

and vandalized. Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



1-23-04 Housing Code Inspector inspected the property, and found the

structure to be vandalized, and neglected, made photographs of the property,

and wrote up "Inspector's Condemnation Report".



3-10-04 Notice of hearing to be held mailed to owner of record.



3-24-04 Hearing held. Forty-five day "Notice to Repair or Demolish" hand

delivered to owner.



3-24-04 Document was prepared per owner's request that the City proceed with

demolition process, waive all time restrictions, request asbestos survey,

receive pricing for demolition, and proceed with demolition. Owner did not

come into office to sign document.



3-24-04 Requested asbestos survey from GLE Associates.



4-16-04 Received asbestos survey from GLE Associates.



4-19-04 Haley Carpenter, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $18,160.00 (Regatta Court) and $13,376.00

(Alpine Dr.), and GLE Associates priced the cost of asbestos survey at

$496.00 (Regatta Ct) and $524.00 (Alpine Dr.), totaling $32,556.00.



5-10-04 Inspections revealed that no progress has been made.



5-13-04 Letter mailed to owner that we had requested asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for

approval of demolition.

CHRONOLOGY

Page 2

June 1, 2004



5-27-04 Re-inspections and new photographs revealed that no progress has been

made.



5-28-04 Letter mailed to owner advising cost of demolition and Council dates.



6-8-04 Ordinance providing for demolition goes to Council for first reading.







STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: MICKLE, Charlie & Ora Lee



ADDRESS: 2827 Bradley Circle



DATE: June 1, 2004



I: LOCATION: Tax Map 7, Block 6, Lot 19



II: BUILDING CONDITION AND CURRENT STATUS



At the time original inspection was made, structure was

dilapidated. Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



1-20-04 Housing Code Inspector inspected the property, and found the

structure to be dilapidated, made photographs of the property, and wrote

up "Inspector's Condemnation Report".



2-11-04 Notice of hearing to be held mailed to owner of record.



2-25-04 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed

to owner.



3-12-04 Ran legal ad.



4-12-04 Inspections revealed that no progress has been made.



4-26-04 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for

approval of demolition.



4-26-04 Requested asbestos survey from GLE Associates.



5-19-04 Received asbestos survey from GLE Associates.



5-25-04 Haley Carpenter, Reaves Wrecking Company, Inc., price the cost of

completing the demolition at $4,905.00 and GLE Associates priced the cost of

asbestos survey at $416.00 totaling $5,321.00.



5-27-04 Re-inspections and new photographs revealed that no progress has been

made.



5-28-04 Letter mailed to owner advising cost of demolition and Council date.

CHRONOLOGY

Page 2

June 1, 2004



6-8-04 Ordinance providing for demolition goes to Council for first reading.





STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: MILLER, Worthy



ADDRESS: 4218 Willis Street



DATE: June 1, 2004



I: LOCATION: Tax Map 90, Block 41, Lot 18



II: BUILDING CONDITION AND CURRENT STATUS



At the time original inspection was made, structure was neglected

and vandalized. Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



12-3-03 Housing Code Inspector inspected the property, and found the

structure to be vandalized and neglected, made photographs of the property,

and wrote up "Inspector's Condemnation Report".



2-11-04 Notice of hearing to be held mailed to owner of record.



2-25-04 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed

to owner.



4-12-04 Inspections revealed that no progress has been made.



4-26-04 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for

approval of demolition.



4-26-04 Requested asbestos survey from GLE Associates.



4-27-04 Ran legal ad.



5-19-04 Received asbestos survey from GLE Associates.



5-25-04 Haley Carpenter, Reaves Wrecking Company, Inc., priced the cost of

completing demolition at $2,989.00 and GLE Associates priced the cost of

asbestos survey at $325.00 totaling $3,314.00.



5-27-04 Re-inspections and new photographs revealed that no progress has been

made.



5-28-04 Letter mailed to owner advising cost of demolition and Council dates.

CHRONOLOGY

Page 2

June 1, 2004



6-8-04 Ordinance providing for demolition goes to Council for first reading.





STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: ROBINSON, Vera M.



ADDRESS: 820 Coolidge Avenue



DATE: June 1, 2004



I: LOCATION: Tax Map 39, Block 15, Lot 2



II: BUILDING CONDITION AND CURRENT STATUS



At the time original inspection was made, structure was neglected.

Owner has done nothing either to repair or demolish.



III: CHRONOLGY



10-20-03 Housing Code Inspector inspected the property, and found the

structure to be neglected, made photographs of the property, and wrote up

"Inspector's Condemnation Report".



2-11-04 Notice of hearing to be held mailed to owner of record.



2-25-04 Hearing held. Forty-five day "Notice to Repair or Demolish" hand

delivered to owner.



4-12-04 Inspections revealed that no progress has been made.



4-26-04 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for first

reading.



4-26-04 Requested asbestos survey from GLE Associates.



5-19-04 Received asbestos survey from GLE Associates.



5-25-04 Haley Carpenter, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $2,028.25 and GLE Associates priced the cost of

asbestos survey at $325.00 totaling $2,353.25.



5-27-04 Re-inspections and new photographs revealed that no progress has been

made.



5-28-04 Letter mailed to owner advising cost of demolition, and Council dates.



6-8-04 Ordinance providing for demolition goes to Council for first reading.





STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: SHYTLE, James Ray



ADDRESS: 1637 Elvan Avenue



DATE: June 1, 2004



I: LOCATION: Tax Map 63, Block 33, Lot 37



II: BUILDING CONDITION AND CURRENT STATUS



At the time original inspection was made, structure was neglected.

Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



1-20-04 Housing Code Inspector inspected the property, and found the

structure to be neglected. Owner has done nothing either to repair or

demolish.



2-11-04 Notice of hearing to be held mailed to owner of record.



2-25-04 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed

to owner.



2-27-04 Ran legal ad.



4-12-04 Inspections revealed that no progress has been made.



4-26-04 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for

approval of demolition.



4-26-04 Requested asbestos survey from GLE Associates.



5-19-04 Received asbestos survey from GLE Associates.



5-25-04 Haley Carpenter, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $5,688.50 and GLE Associates priced the cost of

asbestos survey at $374.00 totaling $6,062.50.



5-27-04 Re-inspections and new photographs revealed that no progress has been

made.



5-28-04 Letter mailed to owner advising cost of demolition and Council dates.



CHRONOLGY

Page 2

June 1, 2004



6-8-04 Ordinance providing for demolition goes to Council for first reading.





STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: SPELLMAN-HUNG CAPITAL, LLC



ADDRESS: 400 - 29th Avenue, Lots 54 & 57



DATE: June 1, 2004



I: LOCATION: Tax Map 48, Block 17, Lot 2



II: BUILDING CONDITION AND CURRENT STATUS



At the time inspection was made, structures were neglected. Owner

has done nothing either to repair or demolish.



III: CHRONOLOGY



11-5-03 Housing Code Inspector inspected the property, and found the

structures to be neglected, made photographs of the property, and wrote up

"Inspector's Condemnation Report".



2-11-04 Notice of hearing to be held mailed to owner of record.



2-25-04 Hearing held. Forty-five day "Notice to Repair or Demolish" hand

delivered to owner.



4-12-04 Inspections revealed that no progress has been made.



4-26-04 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for

approval of demolition.



4-26-04 Requested asbestos survey from GLE Associates.



5-19-04 Received asbestos survey from GLE Associates.



5-25-04 Haley Carpenter, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $3,233.75 and GLE Associates priced the cost of

asbestos survey at $650.00 totaling $3,883.75.



5-27-04 Re-inspections and new photographs revealed that no progress has been

made.



5-28-04 Letter mailed to owner advising cost of demolition and Council dates.



6-8-04 Ordinance providing for demolition goes to Council for first reading.





STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: THOMAS, Jason Wayne



ADDRESS: 920 Benning Drive



DATE: June 1, 2004



I: LOCATION: Tax Map 64, Block 32, Lot 8



II: BUILDING CONDITION AND CURRENT STATUS



At the time original inspection was made, structure was vacant and

vandalized. Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



1-22-04 Housing Code Inspector inspected the property, and found the

structure to be vandalized, made photographs of the property, and wrote up

"Inspector's Condemnation Report".



2-11-04 Notice of hearing to be held mailed to owner of record.



2-25-04 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed

to owner.



3-19-04 Ran legal ad



3-31-04 Inspections revealed that no progress has been made.



4-26-04 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for

approval of demolition.



4-26-04 Requested asbestos survey from GLE Associates.



5-19-04 Received asbestos survey from GLE Associates.



5-25-04 Haley Carpenter, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $18,746.50 and GLE Associates priced the cost of

asbestos survey at $430.00 totaling $19,176.50.



5-27-04 Re-inspections and new photographs revealed that no progress has been

made.



5-28-04 Letter mailed to owner advising cost of demolition and Council dates.

CHRONOLOGY

Page 2

June 1, 2004



6-8-04 Ordinance providing for demolition goes to Council for first reading.