COLUMBUS CONSOLIDATED GOVERNMENT
COUNCIL MEETING
September 10, 2002
Agenda Report #______________
TO: Mayor and Councilors
SUBJECT: Bids for Demolition of Derelict Buildings by City Contract
INITIATED BY: Department of Economic and Community Development
*********************************
Recommendation: Approve the cost of the demolition of nine structures, as
priced by Reaves Wrecking
Company, Inc. A Status Report and Chronology is attached for each structure.
Background: Upon routine investigation, Housing Code Inspectors made
inspections of the properties, took photographs and wrote up the structures
according to the unsafe building ordinance (Section 8-81 - 8-90 of the Columbus
Code of Ordinances). Inspections and Code Enforcement Division notified the
owners of the hearings, held hearings, and then mailed notices to the owners,
giving them 45 days in which to demolish or to repair the structures.
Analysis: On these structures no work has been done. The structures are:
930 Winston Road - Jones, 901 Joy Road Lot K58 - Livsey, 2801 9th Street -
Pitts, 2833 Bradley Circle - Mickle, 358 Bragg Smith Street - Rachal, 4325 Old
Cusseta Rd, Lt 33 - Smith. Some demolition work has been done on the
following: 4756 Kolb Ave. - Fisher and 1605 Sheffield Drive - Snell. Some
repairs have been done on 410 29th Street, Apts 1 & 2 - Montgomery.
Alternatives: The only alternative to the City?s proceeding with the
demolition will be for the owners to complete the demolition of the structures
prior to approval by Council.
Financial Considerations: Demolitions under City contracts are funded by the
Community Development Block Grant Program (CDBG). The City has signed an
annual contract with Reaves Wrecking Company, Inc., to do all of the
demolitions for the City. Upon completion of the demolitions, the City will
pay Reaves with funds from CDBG and will file liens against the properties for
the cost of the demolitions. These liens will have to be repaid to the City
before the owners can sell the properties.
Legal Considerations: All precautions have been taken to assure that the
owners received proper notification of all actions by the City. The annual
contract between Reaves Wrecking Company, Inc., and the City outlines the
responsibility of Reaves in performing their work.
Recommendations/Actions: Approve the costs, as priced by Reaves, for the
demolition of the structures and the clearing of the lots of the debris.
WLDJr:jsd
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: FISHER, James W. & Ollie M.
ADDRESS: 4756 Kolb Avenue
DATE: September 3, 2002
I: LOCATION: Tax Map 32, Block 16, Lot 34
II: BUILDING CONDITION AND CURRENT STATUS
At the time original inspection was made, structure was 30% - 100% rotten and
collapsing. Owner has done nothing either to repair or demolish structure.
III: CHRONOLOGY
9-11-01 Housing Code Inspector inspected the property, found the structure to
be rotten, collapsing and weathered, made photographs of the structure, and
wrote up "Inspector's Condemnation Report".
10-8-01 Owner bought demolition permit.
10-10-01 Notice of hearing to be held mailed to owner of record.
10-24-01 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed to
owner
12-19-01 Inspections revealed that little demolition progress has been made,
sprayed red D.
1-25-02 Letter mailed to owner that we were requesting asbestos survey, after
which we would get price from Reaves Wrecking and send to Council for approval
of demolition.
1-25-02 Requested asbestos survey from GLE Associates.
2-18-02 Received asbestos survey from GLE Associates.
2-20-02 Lisa Talley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $4,592.00 and GLE Associates priced the cost of
asbestos survey at $325.00, totaling $4,917.00.
CHRONOLOGY
Page 2
September 3, 2002
2-21-02 Re-inspections and new photographs revealed that no further progress
has been made.
8-30-02 Letter mailed to owner stating total price of demolition and Council
dates.
9-10-02 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: JONES, Ethel Mae
ADDRESS: 930 Winston Road
DATE: September 3, 2002
I: LOCATION: Tax Map 64, Block 33, Lot 19
II: BUILDING CONDITON AND CURRENT STATUS
At the time original inspection was made, structure was 10% - 100%
dilapidated. Owner has done nothing either to repair of demolish structure.
III: CHRONOLOGY
3-20-02 Housing Code Inspector inspected the property and found the structure
to be dilapidated and vandalized, made photographs of the property, and wrote
up "Inspector's Condemnation Report".
4-10-02 Notice of hearing to be held mailed to owner of record.
4-24-02 Hearing held. Forty-five day "Notice to Repair or Demolish" hand
delivered to owner.
6-10-02 Inspections revealed that no progress had been made, sprayed red D.
6-25-02 Letter mailed to owner that we were requesting asbestos survey, after
which we would get price from Reaves Wrecking, and send to Council for approval
of demolition.
6-25-02 Requested asbestos survey from GLE Associates.
7-19-02 Received asbestos survey from GLE Associates.
7-22-02 Lisa Talley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $4,560.00 and GLE Associates priced the cost of
asbestos survey at $346.00 totaling $4,906.00.
7-23-02 Re-inspections and new photographs revealed that no progress had been
made.
CHRONOLOGY
Page 2
September 3, 2002
8-30-02 Letter mailed to owner of record advising the cost of demolition and
Council dates.
9-10-02 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: LIVSEY, Erik J. & Linda
ADDRESS: 901 Joy Road Lot K-58
DATE: September 3, 2002
I: LOCATION: Tax Map 64, Block 14, Lot 14A
II: BUILDING CONDITON AND CURRENT STATUS
At the time original inspection was made, structure was 40% - 80% dilapidated
and rotten. Owner has done nothing either to repair or demolish structure.
III: CHRONOLOGY
3-26-02 Housing Code Inspector, inspected the property, and found the structure
to be dilapidated and rotten, made photographs of the property, and wrote up
"Inspector's Condemnation Report".
4-10-02 Notice of hearing to be held mailed to owner of record.
4-24-02 Hearing held. Forty-five day "Notice to Repair or Demolish" hand
delivered to owner.
6-10-02 Inspections revealed that no progress had been made, sprayed red D.
6-25-02 Letter mailed to owner that we were requesting asbestos survey, after
which we would get price from Reaves Wrecking, and send to Council for approval
of demolition.
6-25-02 Requested asbestos survey from GLE Associates.
7-18-02 Received asbestos survey from GLE Associates
7-18-02 Ran legal ad
7-22-02 Lisa Talley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $1,540.00 and GLE Associates priced the cost of
asbestos survey at $325.00 totaling $1,865.00.
CHRONOLOGY
Page 2
September 3, 2002
7-23-02 Re-inspections and new photographs revealed that no progress had been
made.
8-30-02 Letter mailed to owner of record advising the cost of demolition and
Council dates.
9-10-02 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: MICKLE, Charlie M & Ora L.
ADDRESS: 2833 Bradley Circle
DATE: September 3, 2002
I: LOCATION: Tax Map 7, Block 6, Lot 20
II: BUILDING CONDITON AND CURRENT STATUS
At the time original inspection was made, structure was 10% - 100%
deteriorated and weathered. Owner has done nothing either to repair or
demolish structure.
III: CHRONOLOGY
1-25-02 Housing Code Inspector inspected the property, and found the structure
to be deteriorated, rotten, and weathered, made photographs of the property,
and wrote up "Inspector's Condemnation Report".
2-13-02 Notice of hearing to be held mailed to owner of record.
2-27-02 Hearing held. Forty-five day "Notice to Repair or Demolish" delivered
to owner.
3-1-02 Owner bought permit to repair. (No inspections have been called for.)
4-10-02 Inspections revealed that no progress had been made, sprayed red D.
7-24-02 Letter mailed to owner that we were requesting asbestos survey, after
which we would get price from Reaves Wrecking, and send to Council for approval
of demolition.
7-24-02 Requested asbestos survey from GLE Associates.
8-21-02 Received asbestos survey from GLE Associates.
8-22-02 Lisa Talley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $3,953.90 and GLE Associates priced the cost of
asbestos removal at $374.00 totaling $4,327.90.
CHRONOLOGY
Page 2
September 3, 2002
8-28-02 Re-inspections and new photographs revealed that no progress has been
made.
8-30-02 Letter mailed to owner of record advising the cost of demolition and
Council dates.
9-10-02 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: MONTGOMERY, Wyndol B.
ADDRESS: 410 - 29th Street Apts 1 & 2
DATE: September 3, 2002
I: LOCATION: Tax Map 15, Block 40, Lot 18
II: BUILDING CONDITON AND CURRENT STATUS
At the time original inspection was made, structure was 50% - 90% rotten, and
poorly maintained. Owner has done little to repair or demolish structure.
III: CHRONOLOGY
9-21-01 Housing Code Inspector inspected the property, and found the structure
to be rotten, dilapidated and poorly maintained, made photographs of the
structure and wrote up "Inspector's Condemnation Report".
10-10-01 Notice of hearing to be held mailed to owner of record.
10-24-01 Hearing held. Forty-five day "Notice to Repair or Demolish" delivered
to owner.
11-16-01 Owner bought permit to repair.
1-15-02 Inspections revealed that some work had begun, work very slow.
4-18-02 Letter mailed to owner that we were requesting asbestos survey, after
which we would get price from Reaves Wrecking, and send to Council for approval
of demolition.
4-18-02 Requested asbestos survey from GLE Associates.
5-9-02 Received asbestos survey from GLE Associates.
5-9-02 Lisa Talley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $5,120.00 and GLE Associates priced the cost of
asbestos survey at $325.00, totaling $5,445.00.
CHRONOLOGY
Page 2
September 3, 2002
5-28-02 Re-inspections and new photographs revealed that no other progress has
been made.
8-30-02 Letter mailed to owner of record advising the cost of demolition and
Council dates.
9-10-02 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: PITTS, Ruby J. & Michael
ADDRESS: 2801 - 9th Street
DATE: September 3, 2002
I: LOCATION: Tax Map 50, Block 25, Lot 2
II: BUILDING CONDITON AND CURRENT STATUS
At the time original inspection was made, structure was 30% - 100% rotten and
dilapidated. Owner has done nothing either to repair or demolish structure.
III: CHRONOLOGY
3-5-02 Housing Code Inspector inspected the property, and found the structure
to be dilapidated and rotten, made photographs of the property, and wrote up
"Inspector's Condemnation Report".
4-10-02 Notice of hearing to be held mailed to owner of record.
4-24-02 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed to
owner.
6-10-02 Inspections revealed that no progress had been made, sprayed red D.
6-25-02 Letter mailed to owner that we were requesting asbestos survey, after
which we would get price from Reaves Wrecking, and send to Council for approval
of demolition.
6-25-02 Requested asbestos survey from GLE Associates.
7-19-02 Received asbestos survey from GLE Associates.
7-22-02 Lisa Talley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $5,140.20 and GLE Associates priced the cost of
asbestos survey at $353.00 totaling $5,493.20.
7-23-02 Re-inspections and new photographs revealed that no progress had been
made.
CHRONOLOGY
Page 2
September 3, 2002
8-30-02 Letter mailed to owner of record advising the cost of demolition and
Council dates.
9-10-02 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: RACHAL, Dorothy M., Life Estate
ADDRESS: 358 Bragg Smith Street
DATE: September 3, 2002
I: LOCATION: Tax Map 41, Block 6, Lot 2
II: BUILDING CONDITON AND CURRENT STATUS
At the time original inspection was made, property was 25% - 60% weathered and
vandalized. Owner has done nothing either to repair or demolish structure.
III: CHRONOLOGY
3-4-02 Housing Code Inspector inspected the property and found the structure to
be weathered and vandalized, made photographs of the property, and wrote up
"Inspector's Condemnation Report".
4-10-02 Notice of hearing to be held mailed to owner of record.
4-24-02 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed to
owner.
4-24-02 Ran legal ad.
6-10-02 Inspections revealed that no progress had been made, sprayed red D.
6-25-02 Letter mailed to owner that we were requesting asbestos survey, after
which we would get price from Reaves Wrecking, and send to Council for approval
of demolition.
6-25-02 Requested asbestos survey from GLE Associates.
7-19-02 Received asbestos survey form GLE Associates.
7-22-02 Lisa Talley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $4,341.00 and GLE Associates priced asbestos
survey at $339.00 totaling $4,680.00.
CHRONOLOGY
Page 2
September 3, 2002
7-23-02 Re-inspections and new photographs revealed that no progress had been
made.
8-30-02 Mailed letter to owner of record advising cost of demolition and
Council dates.
9-10-02 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: SMITH, Eddie C.
ADDRESS: 4325 Old Cusseta Road Lt 33
DATE: September 3, 2002
I: LOCATION: Tax Map 90, Block 5, Lot 1
II: BUILDING CONDITON AND CURRENT STATUS
At the time original inspection was made, structure was 50% - 90%
damaged and poorly maintained. Owner has done nothing either to repair or
demolish structure.
III: CHRONOLOGY
4-29-02 Housing Code Inspector inspected the property and found the structure
to be damaged and poorly maintained, made photographs of the property, and
wrote up "Inspector's Condemnation Report".
5-8-02 Notice of hearing to be held mailed to owner.
5-22-02 Hearing held. Forty-five day "Notice to Repair or Demolish" delivered
to owner.
7-10-02 Inspections revealed that no progress had been made, sprayed red D.
7-24-02 Letter mailed to owner that we were requesting asbestos survey, after
which we would get price from Reaves Wrecking, and send to Council for approval
of demolition.
7-24-02 Requested asbestos survey from GLE Associates.
8-21-02 Received asbestos survey from GLE Associates.
8-22-02 Lisa Talley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $1,644.50 and GLE Associates priced the cost of
asbestos survey at $367.00 totaling $2,011.50.
8-28-02 Re-inspections and new photographs revealed that no progress has been
made.
CHRONOLOGY
Page 2
September 3, 2002
8-30-02 Letter mailed to owner of record advising the cost of demolition and
Council dates.
9-10-02 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: SNELL, James
ADDRESS: 1605 Sheffield Drive (2 Accessory Structures Only)
DATE: September 3, 2002
I: LOCATION: Tax Map 67, Block 17, Lot 20
II: BUILDING CONDITON AND CURRENT STATUS
At the time original inspection was made, structure was 100% rotten. Owner has
done nothing either to repair or demolish structure.
III: CHRONOLOGY
2-20-02 Housing Code Inspector inspected property, and found the structure to
be falling down, and rotten, made photographs of the structure, and wrote up
"Inspector's Condemnation Report".
3-13-02 Notice of hearing to be held mailed to owner of record.
3-27-02 Hearing held. Forty-five day "Notice to Repair or Demolish" delivered
to owner.
5-21-02 Owner bought demolition permit.
6-20-02 Inspections revealed that demo had begun, but has now stopped.
7-24-02 Letter mailed to owner that we were requesting asbestos survey, after
which we would get price from Reaves Wrecking, and send to Council for approval
of demolition.
7-24-02 Requested asbestos survey from GLE Associates.
8-21-02 Received asbestos survey from GLE Associates.
8-22-02 Lisa Talley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $7,603.80 and GLE Associates priced the cost of
asbestos survey at $367.00, totaling $7,970.80.
CHRONOLOGY
Page 2
September 10, 2002
8-28-02 Re-inspections and new photographs revealed that no other progress has
been made.
8-30-02 Letter mailed to owner of record advising cost of demolition and
Council dates.
9-10-02 Ordinance providing for demolition goes to Council for first reading.