Columbus, Georgia
Georgia's First Consolidated Government
Post Office Box 1340
Columbus, Georgia, 31902-1340
(706) 653-4013
fax (706) 653-4016
Council Members
Agenda Item ________
COLUMBUS CONSOLIDATED GOVERNMENT
COUNCIL MEETING
October 7, 2003
Agenda Report #______________
TO: Mayor and Councilors
SUBJECT: Bids for Demolition of Derelict Buildings by City Contract
INITIATED BY: Department of Economic and Community Development
*********************************
Recommendation: Approve the cost of the demolition of nine structures, as
priced by Reaves
Wrecking Company, Inc. A Status Report and Chronology is attached for each
structure.
Background: Upon routine investigation, Housing Code Inspectors made
inspections of the properties, took photographs and wrote up the structures
according to the unsafe building ordinance (Section 8-81 - 8-90 of the Columbus
Code of Ordinances). Inspections and Code Enforcement Division notified the
owners of the hearings, held hearings, and then mailed notices to the owners,
giving them 45 days in which to demolish or to repair the structures.
Analysis: No progress has been made on the following: 3129 & 3133 Schatulga
Rd, Anderson, 3636 St. Mary's Rd Lt D-28, Barton,3466 Marathon Dr, Lot 31,
Nelms, 3200 Tip Top Drive, Rudd, 400 29th Ave, Lot 33, Spellman-Hung, 3137
Schatulga Rd, Willis, 1009 Britt Ave, White. Some progress has been made on
the following, but has ceased: 2213 1st Ave, Jordan.
Alternatives: The only alternative to the City?s proceeding with the
demolition will be for the owners to complete the demolition of the structures
prior to approval by Council.
Financial Considerations: Demolitions under City contracts are funded by the
Community Development Block Grant Program (CDBG). The City has signed an
annual contract with Reaves Wrecking Company, Inc., to do all of the
demolitions for the City. Upon completion of the demolitions, the City will
pay Reaves with funds from CDBG and will file liens against the properties for
the cost of the demolitions. These liens will have to be repaid to the City
before the owners can sell the properties.
Legal Considerations: All precautions have been taken to assure that the
owners received proper notification of all actions by the City. The annual
contract between Reaves Wrecking Company, Inc., and the City outlines the
responsibility of Reaves in performing their work.
Recommendations/Actions: Approve the costs, as priced by Reaves, for the
demolition of the structures and the clearing of the lots of the debris.
WLDJr:jsd
TO COUNCIL - OCTOBER 14th & 21st, 2003
REQUESTED ASBESTOS SURVEY - SEPTMEBER 15th, 2003
INSP. REF # OWNER LOCATION
112 03-0266 ANDERSON, Susie J. 3129 Schatulga Rd.
P.O. Box 6128 (House Only)
Columbus, GA 31917 9766 $7,366.90
112 03-0268 ANDERSON, Susie J. 3133 Schatulga Rd.
P.O. Box 6128 (House Only)
Columbus, GA 31917 9766 $3,568.40
112 03-0350 BARTON, Vanessa 3636 St. Mary's Rd, Lt D28
3636 St. Mary's Rd, Lt D28 (Trailer Only)
Columbus, GA 31906 9865 $2,305.00
cc: M. J. Hyatt % Oak Hill MHP
3536 St. Mary's Rd Office
Columbus, GA 31906
Certified Mail #9872
112 02-0464 JORDAN, W. Richard, Jr. 2213 - 1st Avenue
1481 Mayo Road (House Only)
Ellerslie, GA 31807 9889 $5,189.90
112 03-0461 NELMS, Mamie R. 3466 Marathon Dr, Lt 31
1036 Broadway (Trailer Only)
Columbus, GA 31901 9896 $2,305.00
111 03-0465 RUDD, Roger 3200 Tip Top Drive
1226 Dunbar Ave. (House Only)
Columbus, GA 31906 9902 $4,917.70
112 03-0467 SPELLMAN-HUNG CAPITAL 400 -29th Ave, Lt 33
1415 Dartmouth Road (Trailer Only)
Columbus, GA 31904 9919 $2,305.00
112 03-0272 WILLIS, Willie Clarence 3137 Schatulga Road
% Judy Myles (House Only)
5395 Stillwater Drive 9926 $2,530.00
New Orleans, LA 70128
112 03-0028 WHITE, Naomi Fedd 1009 Britt Avenue
3114 Hammarskjoid (House Only)
Atlanta, GA 30344 9933 $4,607.00
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: ANDERSON, Susie Johnson
ADDRESS: 3133 Schatulga Road
DATE: October 7, 2003
I: LOCATION: Tax Map 113, Block 13, Lot 40
II: CONDITION AND CURRENT STATUS OF BUILDING:
At the time original inspection was made, structure was
dilapidated. Owner has done nothing either to repair or demolish.
III: CHRONOLOGY
3-7-03 Housing Code Inspector inspected the property, and found the
structure to be dilapidated and neglected, made photographs of the
property, and wrote up "Inspector's Condemnation Report".
5-14-03 Notice of hearing to be held mailed to owner of record.
5-28-03 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed
to owner.
7-18-03 Inspections revealed that no progress has been made.
8-20-03 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council
for approval of demolition.
8-20-03 Requested asbestos survey from GLE Associates.
9-15-03 Received asbestos survey from GLE Associates.
9-22-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $6,974.90 and GLE Associates priced the cost of
asbestos survey at $392.00 totaling $7,366.90.
10-1-03 Re-inspections and new photographs revealed that no progress has
been made.
CHRONOLOGY
Page 2
October 7, 2003
10-3-03 Letter mailed to owner advising demolition cost and Council dates.
10-14-03 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: ANDERSON, Susie Johnson
ADDRESS: 3129 Schatulga Road
DATE: October 7, 2003
I: LOCATION: Tax Map 113, Block 13, Lot 40
II: CONDITION AND CURRENT STATUS OF BUILDING:
At the time original inspection was made, structure was dilapidated.
Owner has done nothing either to repair or demolish.
III: CHRONOLOGY
3-7-03 Housing Code Inspector inspected the property, and found the
structure to be dilapidated and neglected, made photographs of the
property, and wrote up "Inspector's Condemnation Report".
5-14-03 Notice of hearing to be held mailed to owner of record.
5-28-03 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed to
owner.
7-18-03 Inspections revealed that no progress has been made.
8-20-03 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council for
approval of demolition.
8-20-03 Requested asbestos survey from GLE Associates.
9-15-03 Received asbestos survey from GLE Associates.
9-22-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $3,222.40 and GLE Associates priced the cost of
asbestos survey at $346.00 totaling $3,568.40.
10-1-03 Re-inspections and new photographs revealed that no progress has
been made.
10-3-03 Letter mailed to owner advising cost of demolition and Council dates.
CHRONOLOGY
Page 2
October 7, 2003
10-14-03 Ordinance providing for demolition goes to Council for first
reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: BARTON, Vanessa
ADDRESS: 3636 St. Mary's Road, Lot D-28
DATE: October 7, 2003
I: LOCATION: Tax Map 65, Block 28, Lot 28
II: CONDITION AND CURRENT STATUS OF BUILDING:
At the time original inspection was made, structure was vandalized
and neglected. Owner has done nothing either to repair or demolish.
III: CHRONONOGLY
4-14-03 Housing Code Inspector inspected the property, and found the
structure to be vandalized, unsecured and neglected, made photographs of
the property, and wrote up "Inspector's Condemnation Report."
5-14-03 Notice of hearing to be held mailed to owner.
5-28-03 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed
to owner.
5-28-03 Ran legal ad.
7-18-03 Inspections revealed that no progress has been made.
8-20-03 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council
for approval of demolition.
8-20-03 Requested asbestos survey from GLE Associates.
9-15-03 Received asbestos survey from GLE Associates.
9-22-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $1,980.00 and GLE Associates priced the cost
of asbestos survey at $325.00 totaling $2,305.00.
10-1-03 Re-inspections and new photographs revealed that no progress has
been made.
CHRONOLOGY
Page 2
October 7, 2003
10-3-03 Letter mailed to owner advising cost of demolition and Council
dates.
10-14-03 Ordinance providing for demolition goes to Council for first
reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: JORDAN, William Richard, Jr.
ADDRESS: 2213 - 1st Avenue
DATE: October 7, 2003
I: LOCATION: Tax Map 06, Block 01, Lot 09
II: CONDITION AND CURRENT STATUS OF BUILDING:
At the time original inspection was made, structure was fire
damaged. Owner has done nothing either to repair or demolish.
III: CHRONOLOGY
6-7-02 Housing Code Inspector inspected the property, and found the
structure to be burned, made photographs of the property, and wrote up
"Inspector's Condemnation Report."
7-10-02 Notice of hearing to be held mailed to owner.
7-24-02 Hearing held. Forty-five day "Notice to Repair or Demolish"
mailed to owner.
9-9-02 Inspections revealed that some work had been done, has ceased.
8-20-03 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council
for approval of demolition.
8-20-03 Requested asbestos survey from GLE Associates.
9-15-03 Received asbestos survey from GLE Associates.
9-22-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $4,864.90 and GLE Associates priced the cost
of asbestos survey at $325.00 totaling $5,189.90.
10-1-03 Re-inspections and new photographs revealed that no progress has
been made.
CHRONOLOGY
Page 2
October 7, 2003
10-3-03 Letter mailed to owner advising cost of demolition and Council
dates.
10-14-03 Ordinance providing for demolition goes to Council for first
reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: NELMS, Mamie R.
ADDRESS: 3466 Marathon Drive Lot 31
DATE: October 7, 2003
I: LOCATION: Tax Map 63, Block 40, Lot 4
II: BUILDING CONDTION AND CURRENT STATUS:
At the time original inspection was made, structure was
neglected. Owner has done nothing either to repair or demolish.
III: CHRONOLOGY
5-5-03 Housing Code Inspector inspected the property, and found the
structure to be neglected and poorly maintained, made photographs of the
property, and wrote up "Inspector's Condemnation Report".
6-11-03 Notice of hearing to be held mailed to owner of record.
6-25-03 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed
to owner.
8-11-03 Inspections revealed that no progress has been made.
8-20-03 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council
for approval of demolition.
8-21-03 Requested asbestos survey from GLE Associates.
9-15-03 Received asbestos survey from GLE Associates.
9-22-03 Scott Crawley, Reaves Wrecking Company, Inc., priced the cost of
asbestos survey at $1,980.00 and GLE Associates priced the cost of asbestos
survey at $325.00 totaling $2,305.00.
10-1-03 Re-inspections and new photographs revealed that no progress has
been made.
CHRONOLOGY
Page 2
October 7, 2003
10-3-03 Letter mailed to owner advising cost of demolition and Council
dates.
10-14-03 Ordinance providing for demolition goes to Council for first
reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: RUDD, Roger
ADDRESS: 3200 Tip Top Drive
DATE: October 7, 2003
I: LOCATION: Tax Map 68, Block 36, Lot 7
II: BUILDING CONDITION AND CURRENT STATUS:
At the time original inspection was made, structure was vacant and
vandalized. Owner has done nothing either to repair or demolish.
III: CHRONOLOGY
5-2-03 Housing Code Inspector inspected the property, and found the
structure to be vacant and vandalized, made photographs of the property, and
wrote up "Inspector's Condemnation Report".
6-11-03 Notice of hearing to be held mailed to owner of record.
6-25-03 Hearing held. Forty-five day "Notice to Repair or Demolish"
delivered to owner.
8-14-03 Inspections revealed that no progress has been made.
8-20-03 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council
for approval of demolition.
8-20-03 Requested asbestos survey from GLE Associates.
9-15-03 Received asbestos survey from GLE Associates.
9-22-03 Scott Cawley, Reaves Wrecking Company, Inc. priced the cost of
completing the demolition at $4,571.70 and GLE Associates priced the cost of
asbestos survey at $346.00 totaling $4,917.70.
10-1-03 Re-inspections and new photographs revealed that no progress has
been made.
CHRONOLOGY
Page 2
October 7, 2003
10-3-03 Letter mailed to owner advising cost of demolition and Council
dates.
10-14-03 Ordinance providing for demolition goes to Council for first
reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: SPELLMAN-HUNG CAPITAL, LLC
ADDRESS: 400 29th Avenue, Lot 33
DATE: October 7, 2003
I: LOCATION: Tax Map 45, Block 17, Lot 2
II: BUILDING CONDITION AND CURRENT STATUS:
At the time original inspection was made, structure was vandalized
and neglected. Owner has done
III: CHRONOLGY
5-6-03 Housing Code Inspector inspected the property, and found the
structure to be neglected and vandalized. Owner had done nothing either to
repair or demolish.
6-11-03 Notice of hearing to be held mailed to owner.
6-25-03 Hearing held. Forty-five day "Notice to Repair or Demolish" hand
delivered to owner.
8-11-03 Inspections revealed that no progress has been made.
8-20-03 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council for
approval of demolition.
8-20-03 Requested asbestos survey from GLE Associates.
9-15-03 Received asbestos survey from GLE Associates.
9-22-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $1,980.00 and GLE Associates priced the cost
of asbestos survey at $325.00 totaling $2,305.00.
10-1-03 Re-inspections and new photographs revealed that no progress has been
made.
10-3-03 Letter mailed to owner advising cost of demolition and Council dates.
CHRONOLOGY
Page 2
October 7, 2003
10-14-03 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: WILLIS, Willie Clarence
ADDRESS: 3137 Schatulga Road
DATE: October 7, 2003
I: LOCATION: Tax Map 113, Block 13, Lot 37
II: BUILDING CONDTION AND CURRENT STATUS:
At the time original inspection was made, structure was neglected.
Owner has done nothing either to repair or demolish.
III: CHRONOLOGY
3-7-03 Housing Code Inspector inspected the property, and found the
structure to be poorly maintained and neglected, made photographs of the
property, and wrote up "Inspector's Condemnation Report".
5-14-03 Notice of hearing to be held mailed to owner of record.
5-28-03 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed
to owner.
7-18-03 Inspections revealed that no progress has been made.
8-20-03 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council for
approval of demolition.
8-20-03 Requested asbestos survey from GLE Associates.
9-15-03 Received asbestos survey from GLE Associates.
9-22-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $2,205.00 and GLE Associates priced the cost of
asbestos survey at $325.00 totaling $2,530.00.
10-1-03 Re-inspections and new photographs revealed that no progress has been
made.
10-3-03 Letter mailed to owner advising cost of demolition and Council dates.
CHRONOLOGY
Page 2
October 7, 2003
10-14-03 Ordinance providing for demolition goes to Council for first reading.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: WHITE, Naomi Fedd
ADDRESS: 1009 Britt Avenue
DATE: October 7, 2003
I: LOCATION: Tax Map 38, Block 4, Lot 11
II: BUILDING CONDITION AND CURRENT STATUS:
At the time original inspection was made, structure was neglected.
Owner has done nothing either to repair or demolish.
III: CHRONOLOGY
11-21-02 Housing Code Inspector inspected the property, and found the
structure to be water damaged and neglected, made photographs of the
property, and wrote up "Inspector's Condemnation Report".
1-8-03 Notice of hearing to be held mailed to owner of record.
1-22-03 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed
to owner.
3-11-03 Inspections revealed that no progress has been made.
3-18-03 Local builder called and advised that he was purchasing this
property to repair, pending payment of outstanding loans, taxes, etc.
8-03 Sale did not go through
8-20-03 Letter mailed to owner that we were requesting asbestos survey,
after which we would get price from Reaves Wrecking, and send to Council for
approval of demolition.
8-20-03 Requested asbestos survey from GLE Associates.
9-15-03 Received asbestos survey from GLE Associates.
9-22-03 Scott Cawley, Reaves Wrecking Company, Inc. priced the cost of
completing the demolition at $4,275.00 and GLE Associates priced the cost of
asbestos survey at $332.00 totaling $4,607.00.
CHRONOLOGY
Page 2
October 7, 2003
10-1-03 Re-inspections and new photographs revealed that no progress has been
made.
10-3-03 Letter mailed to owner advising cost of demolition and Council dates.
10-14-03 Ordinance providing for demolition goes to Council for first reading.