DECEMBER 11, 2001
The regular monthly meeting of the Board of Water Commissioners of
Columbus, Georgia, was held at the office of the Columbus Water Works on
Monday, December 11, 201, at 1:30 p.m., the following Commissioners being
present:
James Yancey, Chairman
Kathelen Spencer, Treasurer
Leon Siegel
Harry Vernon
Mayor Bobby Peters
Receipt of the Minutes of the November 12, 2001, meeting was
acknowledged by the Board and approved a written.
President Turner announced to the Board that the Water Works received
three more awards during the past month. They are as follows:
1. State of Georgia Distribution and Collection System Award
2. State of Georgia Wastewater Collection System Award
3. Project Safety Award for the Public Sector
President Turner informed the Board that after receiving these three awards,
the Water Works has received a total of 19 state, regional and national awards
during the year 2001. Chairman Yancey spoke on behalf of the Board in saying
how proud they were of the whole staff for their hard work and accomplishments.
Next, Chairman Yancey recognized Tony Mercer of Fountain, Arrington, Bass,
Mercer & Lee to present the Water Works? Annual Audit Report. Following a
brief summary, the Board acknowledged receipt of this year?s Audit Report.
Management presented the reports from the Division of Operations, Division of
Engineering and Division of Environmental and Information Services. Following
each presentation, the Board acknowledged the Division Reports for the month of
November.
Management reminded the Board that at last months meeting they were advised
that through the efforts of Congressman Mac Collins the Water Works was able to
get appropriations in the amount of $1.5 million. This $1.5 million would go
towards the process to produce Class A Biosolids at the South Columbus Water
Resources Facility.
The project is provided in three phases. The first phase is Facility Planning
and involves the following:
1) Protocol Development
2) Construction and Testing of a full scale reactor for its plug
flow capacity
3) Pilot Scale Testing at a university to demonstrate the effectiveness
of pathogen destruction by the plug flow thermophilic process
4) Reporting, Peer Review and acceptance of the process by EPSA
Phase Two of this project is the design and Phase Three is the construction and
testing. Phase one and Phase Two can be completed with approved funds on the
basis of 55% federal share and 45% local share. Management advised that the
Water Works cost for Phases One and Two would be about $1.4 million to be paid
from the State Revolving Fund Program. The Georgia Environmental Facilities
Authority, who manages the SRF Program, has indicated that money is available
for use on this project. Management informed the Board that if successful an
estimated payback to the Water Works is about five years due to lower costs for
biosolids disposal.
Following discussion, motion was made and seconded authorizing Management to
proceed with this project. Motion carried.
Management advised the Board that funding for work by the Department of
Transportation (DOT) contractors on several road projects, specifically the
Macon Road Widening, was provided from reserve funds ($700,000) during
development from the current budget. The DOT consolidated two separate
projects severely compacting the Water Works time allowed for utility
relocation work. Management stated that in order to meet the new schedule and
avoid conflict with the DOT it is necessary that the work bid on Macon Road be
contracted while recognizing that the funding shortfall is provided from the
Fiscal 2002-03 Budget.
Management reminded the Board that at last months meeting they approved $1.2
million in the design of projects in anticipation that the U.S. Congress would
pass an Economic Stimulus Bill containing funds for water and wastewater
projects. At this time, water and wastewater funding has been dropped,
therefore the proposed design work has been suspended until funding can be
reinstated by Congress.
Management accepted bids on December 4th for water and sewer line adjustments
in conjunction with the DOT Macon Road Widening Project. The work involves
the relocation of 11,000 LF of 6?, 10?, 12? and 16? water main, and the
relocation of 170 LF of gravity sewer. The following bids were received:
Gordy Construction Company $989,558
Jones General Contracting No Bid
Following review of the bid and scope of work, staff has value engineered a
cost savings of $138,640.00, reducing the contract amount to $850,918.00
After discussion, motion was made and seconded authorizing Management to award
the Macon Road Widening Water and Sewer Adjustment Project to Gordy
Construction Company in the amount of $850,918.00. Motion carried.
The Financial Report for the month of November, along with the Meter Reading,
Employee Services and Customer Service?s Reports, were presented to the
Board. Following discussion, motion was made and seconded to accept the
reports. Motion carried.
Following the Financial Report, Secretary Blount reminded the Board of an
earlier report presented at the July Board meeting called ?Customer Oriented
Operations Optimization (CO3) Report?. The recommendations that came out of
this report are as follows:
1. Increase the hours when customer service is available:
Current Customer Service Officer Hours
Lobby Hours 9:00 a.m. ? 5:00 p.m. 8 hrs/day
Drive-Thru 8:00 a.m. ? 5:00 p.m. 9 hrs/day
Telephone Service 8:00 a.m. ? 5:00 p.m. 9 hrs/day
Meter Services 8:30 a.m. ? 5:00 p.m. 8.5 hrs/day
(?on call? crew available until 9:00 p.m.)
Proposed Customer Service Office Hours
Lobby Hours 9:00 a.m. ? 5:00 p.m. 8 hrs/day
Drive-Thru 7:00 a.m. ? 7:00 p.m. 12 hrs/day
Telephone Service 7:00 a.m. ? 7:00 p.m. 12 hrs/day
Meter Services 7:00 a.m. ? 7:00 p.m. 12 hrs/day
2. Allow water service to be restored, following a cut-off for
non-payment, without the customer being home:
The proposed policy and release of liability in support of this recommendation
have been reviewed and endorsed by our attorney.
3. Reduce the hours when water service restoration is available,
following a cut-off for non-payment:
The CO3 report recommends establishing a deadline for submission of payments in
order for customers to receive ?same-day? service. The recommended deadline
for this policy is 2:00 p.m., rather than the current 5:00 p.m. Implementing
this change will significantly reduce the overtime expenditures for the Meter
Services Department.
4. Increase public communications efforts:
Recommended action ? Purchase more media contact with customers.
5. Lengthen the meter reading/billing cycle:
A comprehensive cost analysis does not support a change at this time.
6. Invest in improving the quality of interaction between CWW
representatives and customers:
Establish a regular in-service training program for customer service
representatives and cashiers ? recommendation to be included as part of the FY
02-03 Budget process.
Routinely phone customers prior to a scheduled on-site visit; implement routine
follow-up phone calls after an on-site visit ? process currently being reviewed
by Information Services Department for viability as an automated process.
After discussion, Secretary Blount recommended that these policies become
effective February 2002. During the month of January, bill inserts outlining
these changes will be utilized. As a follow-up, inserts will accompany the
February ? April bills. The Secretary will give a follow-up report to the
Board at its May Board meeting. Motion was made and seconded to approve these
changes. Motion carried. President Turner informed the Board that the Water
Works is observing its 100th Anniversary December 2002, and kicked it off by
the Christmas lighting ceremony on November 26th at the North Columbus Water
Resource Facility. President Turner advised the Board that they have proposed
an outline of activities to do throughout the year in recognition of the Water
Works? history. Also, President Turner advised that they have had a
preliminary discussion with Richard Hyatt on going back through the newspapers
and chronicle the history of the Water Works subject to Board approval.
President Turner informed the Board that it would take approximately $150,000
to achieve such events, which includes establishing two additional scholarship
funds. Management hopes to raise most of these funds through sponsorships and
contributions from consultants, contractors, equipment suppliers, etc. In the
event the Water Works cannot fully fund these events through contributions,
Management requested that reserve funds be utilized to make up any
difference. Following discussion, motion was made and seconded authorizing
Management to proceed with these events. Motion carried.
Next, President Turner wanted to make the Board aware of a request from
Mr. Isaiah Hugley, Deputy City Manager, to allow two members of the Youth
Advisory Council, sponsored by the School Board and City Council, to
participate in a non-voting manner in the Board?s activity. After discussion,
the Board acknowledged this request.
Management provided copies of letters thanking members of the staff for
their participation and services provided from various organizations and
individuals. The Board acknowledged Management?s report.
There being no further business the senior staff and the Board went into
Executive Session to discuss a real estate and legal matter. No action was
taken. The meeting was adjourned.
_________________________________
Emory E. Blount, Secretary