Columbus, Georgia

Georgia's First Consolidated Government

Post Office Box 1340
Columbus, Georgia, 31902-1340
(706) 653-4013
fax (706) 653-4016
Council Members
(D) STORM PIPE REPLACEMENT AT RIVER MILL ANTIQUE MALL



It is requested that Council approve a contract with Warr Grading Contractor,

Inc., in the amount of $23,069.00 to replace storm pipe at River Mill Antique

Mall in Bibb City.



The storm pipe replacement project site is adjacent to the Bibb Mill parking

lot. Warr Grading Contractor is currently replacing the storm pipe that runs

underneath the Bibb Mill parking lot; and the owner of Bibb Mill will pay for

this portion of the work. The section of the pipe that is connected to, but

extends beyond, Bibb Mill parking lot requires replacement as well, and the

City is responsible for this portion of the pipe replacement. Since the City?s

project is in such close proximity to the project in process at Bibb Mill

parking lot, it is only prudent to contract with the contractor who is already

on site, rather than expending the time and cost of formally bidding the

project. In addition, having two contractors on the same site could prove

counter-productive by doubling the traffic congestion and other inconveniences.



The contractor has inspected the site, reviewed the plans provided by the

Engineer, Jordan, Jones and Goulding, and submitted a lump sum cost proposal,

to the Engineering Department, to replace the pipe. The work will include the

following:

Demolition (Asphalt, Curb and Gutter Wall)

Install new 36? RCP as per Plans,

Trench Stabilization as needed

Install New Junction Box

New Storm Manhole to accommodate new pipe

Replace wall as needed

Replace curb and gutter as needed

Replace asphalt paving as needed

Traffic Control as needed

Construction staking

Soils testing as needed



The Engineering Department and the City?s contracted Engineer is confident this

vendor can perform the work, and the cost proposed is comparable to the cost

that is typical for this type of project. The vendor has agreed to provide the

necessary bonding and insurance required for this project.



Funds are budgeted in the FY04 Budget; Lease/Revenue Bonds - 2003A Series Bond

Project ? Drainage/Street Improvements ? Storm Water Enhancements;

0554-200-2439-CBA-7622-40235030.



?ITEM D?



A RESOLUTION



NO. ________



A RESOLUTION AUTHORIZING A CONTRACT WITH WARR GRADING CONTRACTOR, INC.,

IN THE AMOUNT OF $23,069.00 TO REPLACE STORM PIPE AT RIVER MILL ANTIQUE MALL IN

BIBB CITY.



WHEREAS, The storm pipe replacement project site is adjacent to the

Bibb Mill parking lot. Warr Grading Contractor is currently replacing the

storm pipe that runs underneath the Bibb Mill parking lot; and the owner of

Bibb Mill will pay for this portion of the work. The section of the pipe that

is connected to, but extends beyond, Bibb Mill parking lot requires replacement

as well, and the City is responsible for this portion of the pipe replacement.

Since the City?s project is in such close proximity to the project in process,

at Bibb Mill parking lot, it is only prudent to contract with the contractor

who is already on site, rather than expending the time and cost of formally

bidding the project. In addition, having two contractors on the same site

could prove counter-productive by doubling the traffic congestion and other

inconveniences; and,

.

WHEREAS, The contractor has inspected the site, reviewed the plans

provided by the Engineer, Jordan, Jones and Goulding, and submitted a lump sum

cost proposal, to the Engineering Department. The Engineering Department and

the City?s contracted Engineer is confident this vendor can perform the work,

and the cost proposed is comparable to the cost that is typical for this type

of project. The vendor has agreed to provide the necessary bonding and

insurance required for this project.





NOW, THEREFORE, THE COUNCIL OF COLUMBUS, GEORGIA, HEREBY RESOLVES AS FOLLOWS:



That the City Manager is hereby authorized to enter into a contract

with Warr Grading Contractor, Inc., in the amount of $23,069.00 to replace

storm pipe at River Mill Antique Mall in Bibb City. Funds are budgeted in the

FY04 Budget; Lease/Revenue Bonds - 2003A Series Bond Project ? Drainage/Street

Improvements ? Storm Water Enhancements; 0554-200-2439-CBA-7622-40235030.

________________________________________



Introduced at a regular meeting of the Council of Columbus, Georgia, held

the _________ day of _________________, 2004 and adopted at said meeting by the

affirmative vote of _________ members of said Council.



Councilor Allen voting __________.

Councilor Anthony voting __________.

Councilor Davis voting __________ .

Councilor Henderson voting __________.

Councilor Hunter voting __________.

Councilor McDaniel voting __________.

Councilor Turner Pugh voting __________.

Councilor Rodgers voting __________.

Councilor Suber voting __________.

Councilor Woodson voting __________.





_______________________________ _____________________________

Tiny B. Washington, Clerk of Council Robert Poydasheff, Mayor

Back to List