COLUMBUS CONSOLIDATED GOVERNMENT
COUNCIL MEETING
September 2, 2003
Agenda Report #______________
TO: Mayor and Councilors
SUBJECT: Bids for Demolition of Derelict Buildings by City Contract
INITIATED BY: Department of Economic and Community Development
*********************************
Recommendation: Approve the cost of the demolition of two structures, as
priced by Reaves
Wrecking Company, Inc. A Status Report and Chronology is attached for each
structure.
Background: Upon routine investigation, Housing Code Inspectors made
inspections of the properties, took photographs and wrote up the structures
according to the unsafe building ordinance (Section 8-81 - 8-90 of the Columbus
Code of Ordinances). Inspections and Code Enforcement Division notified the
owners of the hearings, held hearings, and then mailed notices to the owners,
giving them 45 days in which to demolish or to repair the structures.
Analysis: No progress has been made on the following: 4621 Holly Avenue,
Pollard and 4766 Kolb Ave.,1 & 2, Huling.
Alternatives: The only alternative to the City?s proceeding with the
demolition will be for the owners to complete the demolition of the structures
prior to approval by Council.
Financial Considerations: Demolitions under City contracts are funded by the
Community Development Block Grant Program (CDBG). The City has signed an
annual contract with Reaves Wrecking Company, Inc., to do all of the
demolitions for the City. Upon completion of the demolitions, the City will
pay Reaves with funds from CDBG and will file liens against the properties for
the cost of the demolitions. These liens will have to be repaid to the City
before the owners can sell the properties.
Legal Considerations: All precautions have been taken to assure that the
owners received proper notification of all actions by the City. The annual
contract between Reaves Wrecking Company, Inc., and the City outlines the
responsibility of Reaves in performing their work.
Recommendations/Actions: Approve the costs, as priced by Reaves, for the
demolition of the structures and the clearing of the lots of the debris.
WLDJr:jsd
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: HULING, Robert
ADDRESS: 4766 Kolb Avenue
DATE: August 5, 2003
I: LOCATION: Tax Map 32, Block 16, Lot 31
II: BUILDING CONDITION AND CURRENT STATUS:
At the time original inspection was made, structure # 2 was 100% fire
damaged. Structure #1 has been altered several times without permits and
does not meet code. Owner perished in the fire.
III: CHRONOLOGY
2-7-03 Housing Code Inspector inspected the property, and found the structure
to be fire damaged, made photographs of the structure, and wrote up
"Inspector's Condemnation Report".
3-12-03 Notice of hearing to be held mailed to owner of record.
3-26-03 Hearing held. Forty-five day "Notice to Repair or Demolish" hand
delivered to owner.
4-4-03 Building permit purchased for structure #1
6-4-03 Inspections revealed that structure #2, the burned unit in the rear,
has been demolished.
6-6-03 Letter mailed to owner that we were requesting asbestos survey, after
which we would get price from Reaves Wrecking, and send to Council for
approval of demolition.
6-6-03 Requested asbestos survey from GLE Associates.
7-10-03 Received asbestos survey from GLE Associates.
7-18-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $4,189.00 and GLE Associates priced the cost of
asbestos survey at $325.00 totaling $4,514.00.
7-28-03 Re-inspections and new photographs revealed that minor work has been
done to eaves.
CHRONOLOGY
Page 2
August 5, 2003
7-30-03 Letter mailed to owner advising the cost of demolition and Council
dates.
8-12-03 Ordinance providing for demolition goes to Council for first reading.
This house is still in the name of the deceased owner.
STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE
OWNER: POLLARD, Precious
ADDRESS: 4621 Holly Avenue
DATE: August 5, 2003
I: LOCATION: Tax Map 32, Block 40, Lot 11
II: BUILDING CONDITION AND CURRENT STATUS:
At the time original inspection was made, structure was dilapidated.
Owner has done nothing either to repair or demolish.
III: CHRONOLOGY
8-16-01 House was written up for repairs, during the Community Improvement
Program in the Bealwood Area.
5-2-02 Permit purchased for new roof.
2-4-03 Housing Code Inspector inspected the property and found the structure to
be dilapidated, and not maintained, made photographs of the property, and
wrote up "Inspector's Condemnation Report".
3-12-03 Notice of hearing to be held mailed to owner of record.
3-26-03 Hearing held. Forty-five day "Notice to Repair or Demolish" delivered
to owner.
5-14-03 Inspections revealed that no progress has been made, sprayed red D.
5-20-03 Building permit purchased, no progress made.
6-6-03 Letter mailed to owner that we were requesting asbestos survey, after
which we would get price from Reaves Wrecking, and send to Council for
approval of demolition.
6-6-03 Requested asbestos survey from GLE Associates.
7-10-03 Received asbestos survey from GLE Associates.
7-18-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of
completing the demolition at $12,355.00 and GLE Associates priced the cost of
asbestos survey at
$346.00 totaling $12,701.00.
CHRONOLOGY
Page 2
August 5, 2003
7-28-03 Re-inspections and new photographs revealed that no progress has been
made.
7-30-03 Letter mailed to owner advising the cost of demolition and Council
dates.
8-12-03 Ordinance providing for demolition goes to Council for first reading.