TO: Mayor and Councilors



SUBJECT: Bids for Demolition of Derelict Buildings by City Contract



INITIATED BY: Department of Economic and Community Development



*********************************



Recommendation: Approve the cost of the demolition of thirteen structures, as

priced by Reaves

Wrecking Company, Inc. A Status Report and Chronology is attached for each

structure.



Background: Upon routine investigation, Housing Code Inspectors made

inspections of the properties, took photographs and wrote up the structures

according to the unsafe building ordinance (Section 8-81 - 8-90 of the Columbus

Code of Ordinances). Inspections and Code Enforcement Division notified the

owners of the hearings, held hearings, and then mailed notices to the owners,

giving them 45 days in which to demolish or to repair the structures.



Analysis: No progress has been made on the following: 3751 Cusseta Road,

Allen, 4333 Hancock Road, Aplin, 1006 Calvin Avenue, Brown, 2900 Veterans

Parkway, Coley, 2310 N. Andrews Circle, Hollis, 6747 Mitchell Drive, Jackson,

1415 -29th Street, Jordan, 621 Radcliff Avenue, Roberson, 44 & 46 Muscogee

Drive, Ryder, 2004 - 3rd Avenue, Tew and 3042 Knox Street 1&2, U. S. Bank

National. Some progress has been made on the following: 2901 Colorado Street,

Carter, 336 Clover Avenue, Rear, James.



Alternatives: The only alternative to the City?s proceeding with the

demolition will be for the owners to complete the demolition of the structures

prior to approval by Council.



Financial Considerations: Demolitions under City contracts are funded by the

Community Development Block Grant Program (CDBG). The City has signed an

annual contract with Reaves Wrecking Company, Inc., to do all of the

demolitions for the City. Upon completion of the demolitions, the City will

pay Reaves with funds from CDBG and will file liens against the properties for

the cost of the demolitions. These liens will have to be repaid to the City

before the owners can sell the properties.



Legal Considerations: All precautions have been taken to assure that the

owners received proper notification of all actions by the City. The annual

contract between Reaves Wrecking Company, Inc., and the City outlines the

responsibility of Reaves in performing their work.



Recommendations/Actions: Approve the costs, as priced by Reaves, for the

demolition of the structures and the clearing of the lots of the debris.



WLDJr:jsd









STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: ALLEN, Joe, Jr.



ADDRESS: 3751 Cusseta Road Lot 8



DATE: March 4, 2003



I: LOCATION: Tax Map 64, Block 16, Lot 16



II: BUILDING CONDITION AND CURRENT STATUS:



At the time original inspection was made, structure was 20% - 75% vandalized.

Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



8-15-02 Housing Code Inspector inspected the property, and found the structure

to be vandalized, abandoned and neglected, made photographs of the structure,

and wrote up "Inspector's Condemnation Report".



9-11-02 Notice of hearing to be held mailed to owner of record.



9-25-02 Hearing held. Forty-five day "Notice to Repair or Demolish" delivered

to owner.



11-14-02 Inspections revealed that no progress has been made, sprayed red D.



1-22-03 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for approval

of demolition.



1-22-03 Requested asbestos survey from GLE Associates.



2-19-03 Ran legal ad.



2-21-03 Received asbestos survey from GLE Associates.



2-26-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $600.00 and GLE Associates priced the cost of

asbestos survey at $325.00 totaling $925.00.



2-26-03 Re-inspections and new photographs revealed that no progress has been

made.



2-27-03 Letter mailed to owner advising the cost of demolition and Council

dates.

CHRONOLOGY

Page 2

March 4, 2003



3-11-03 Ordinance providing for demolition goes to Council for first reading.





STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: APLIN, Amber Lee



ADDRESS: 4333 Hancock Road



DATE: March 4, 2003



I: LOCATION: Tax Map 79, Block 04, Lot 06



II: BUILDING CONDITION AND CURRENT STATUS:



At the time original inspection was made, structure was 80% -100% dilapidated.

Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



3-8-02 Housing Code Inspector inspected the property, and found the structure

to be dilapidated, collapsing, and unsafe, made photographs of the structure,

and wrote up "Inspector's Condemnation Report".



4-10-02 Notice of hearing to be held mailed to owner of record.



4-24-02 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed to

owner.



6-10-02 Inspections revealed that no progress has been made, sprayed red D.



7-10-02 The mother of owner advised that she would get property put into her

name and have demolished. An extension was granted until October 1st.



10-8-02 Re-inspections revealed that no progress has been made.



1-22-03 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for approval

of demolition.



1-22-03 Requested asbestos survey from GLE Associates.



2-19-03 Ran legal ad.



2-21-03 Received asbestos survey from GLE Associates.



2-26-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of

demolition at $2,989.00 and GLE Associates priced the cost of asbestos survey

at $346.00 totaling $3,335.00.



CHRONOLOGY

Page 2

March 4, 2003



2-26-03 Re-inspections and new photographs revealed that no progress has been

made.



2-27-03 Letter mailed to owner advising cost of demolition and Council dates.



3-11-03 Ordinance providing for demolition goes to Council for first reading.





STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: BROWN, Michael O. & Betty J.



ADDRESS: 1006 Calvin Avenue



DATE: March 4, 2003



I: LOCATION: Tax Map 64, Block 34, Lot 20



II: BUILDING CONDITION AND CURRENT STATUS:



At the time original inspection was made, structure was 75% - 100% fire

damaged. Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



10-2-02 Housing Code Inspector inspected the property, and found the structure

to be fire damaged, made photographs of the structure, and wrote up

"Inspector's Condemnation Report".



11-13-02 Notice of hearing to be held mailed to owner of record.



11-27-02 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed to

owner.



12-15-02 Ran legal ad.



1-15-03 Inspections revealed that no progress has been made, sprayed red D.



1-22-03 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for approval

of demolition.



1-22-03 Requested asbestos survey from GLE Associates.



2-19-03 Received asbestos survey from GLE Associates.



2-26-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $7,877.00 and GLE Associates priced the cost of

asbestos survey at $374.00 totaling $8,251.00.



2-26-03 Re-inspections and new photographs revealed that no progress has been

made.



2-27-03 Letter mailed to owner advising the cost of demolition and Council

dates.



CHRONOLOGY

Page 2

March 4, 2003



3-11-03 Ordinance providing for demolition goes to Council for first reading.







STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: CARTER, Ricket Damon



ADDRESS: 2901 Colorado Street



DATE: March 4, 2003



I: LOCATION: Tax Map 50, Block 11, Lot 02



II: BUILDING CONDITION AND CURRENT STATUS:



At the time original inspection was made, structure was 10% - 70%

deteriorated. Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



8-27-02 Housing Code Inspector inspected the property, and found the structure

to be deteriorated and unsafe, made photographs of the structure, and wrote up

"Inspector's Condemnation Report".



9-3-02 Owner bought permit to repair. (Has not called for any inspections.)



10-9-02 Notice of hearing to be held mailed to owner of record.



10-23-02 Hearing held. Forty-five day "Notice to Repair or Demolish" delivered

to owner.



12-12-03 Reinspections revealed that work done did not meet code, job was

tagged, and extension was granted, and upon re-inspection in January, no other

progress has been made.



1-22-03 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for approval

of demolition.



1-22-03 Requested asbestos survey from GLE Associates.



2-19-03 Received asbestos survey from GLE Associates.



2-26-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $2,745.00 and GLE Associates priced the cost of

asbestos survey at $325.00 totaling $3,070.00.







CHRONOLOGY

Page 2

March 3, 2003



2-26-03 Re-inspections and new photographs revealed that no other progress has

been made.



2-27-03 Letter mailed to owner advising demolition costs and Council dates.



3-11-03 Ordinance providing for demolition goes to Council for first reading.





STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: COLEY, James D.



ADDRESS: 2900 Veterans Parkway



DATE: March 4, 2003



I: LOCATION: Tax Map 15, Block 16, Lot 01



II: BUILDING CONDITION AND CURRENT STATUS:



At the time original inspection was made, structure was dilapidated. Owner has

done nothing either to repair or demolish.



III: CHRONOLGY



8-20-02 Housing Code Inspector inspected the property, and found the structure

to be dilapidated and collapsing, made photographs of the structure, and wrote

up "Inspector's Condemnation Report".



10-9-02 Notice of hearing to be held mailed to owner of record.



10-23-02 Hearing held. Forty-five day "Notice to Repair or Demolish" delivered

to owner.



12-12-02 Inspections revealed that no progress has been made, sprayed red D.



1-22-03 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for approval

of demolition.



1-22-03 Requested asbestos survey from GLE Associates.



2-19-03 Ran legal ad.



2-21-03 Received asbestos survey from GLE Associates.



2-26-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $6,840.00 and GLE Associates priced the cost of

asbestos survey at $475.00 totaling $7,315.00.



2-26-03 Re-inspections and new photographs revealed that no progress has been

made.





CHRONOLOGY

Page 2

March 4, 2003



2-27-03 Letter mailed to owner advising the cost of demolition and Council

dates.



3-11-03 Ordinance providing for demolition goes to Council for first reading.







STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: HOLLIS, Geraldine



ADDRESS: 2310 N. Andrews Circle



DATE: March 4, 2003



I: LOCATION: Tax Map 41, Block 26, Lot 08



II: BUILDING CONDITION AND CURRENT STATUS:



At the time original inspection was made, structure was 5% - 15% fire damaged.

Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



5-25-99 Housing Code Inspector inspected the property, found the structure to

be fire damaged, made photographs of the property, and wrote up "Inspector's

Condemnation Report".



6-9-99 Notice of hearing to be held mailed to owner of record.



6-23-99 Hearing held. Forty-five day "Notice to Repair or Demolish" delivered

to owner's mother.



8-25-99 Inspections revealed that structure had been boarded up, sprayed red D.

(Further investigation revealed that insurance company boarded up

house.)



9-17-99 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for approval

of demolition.



9-21-99 Ms. Hollis called after receiving asbestos letter, she has not received

insurance check to repair house.



9-22-99 Housing Code Coordinator talked with Lt. Robert Walker, Arson

Investigator Columbus Fire Department, house burned 5-25-99, caused by wires in

basement, Inspections & Code was informed and Housing Code Inspector condemned

the property. A second fire occurred 5-31-99, illegal tenant ran electric cord

from house next door and fire was caused by smoking in bed.

Columbus Fire Department is finished with physical evidence.









CHRONOLOGY

Page 2

March 4, 2003



9-27-99 Per Bill Hardegree, attorney with insurance company wanted Ms. Hollis

to answer questions and sign papers, etc. Ms. Hollis would not cooperate and

the insurance company could not locate her. There is apparently no settlement

pending with her as she will not cooperate with insurance company.



10-8-99 Attorney Jim Patrick called and talked with Bill Duck. He will assist

Ms. Hollis in dealing with insurance company. Will keep us informed of

progress.



11-17-99 Housing Code Coordinator called Jim Patrick, Attorney, for status

update. He advised that insurance had not paid and that they want Ms. Hollis

to settle for less money than replacement costs.

Housing Code Coordinator responded to a call from Cathy Morgan, 1st

Union Bank, they are the insurance beneficiary and have filed a proof of loss.

Ms. Morgan wanted to know if we will allow Ms. Hollis to rebuild. Housing Code

Coordinator advised her that we would. The bank will administer the funds for

renovation once the insurance has paid.



2-23-00 Housing Code Coordinator call Mr. Hardegree, who advised her that Ms.

Hollis had not given statement under oath. Ms. Hollis had called him the day

before the exam and stated that she could not appear, but that her attorney,

who she refused to name, would contact him. Mr. Hardegree has heard nothing

from attorney. In May, the statue of limitations will expire (May 31, 2000).

Mr. Hardegree will call Jim Patrick, any correspondence will be copied to us.



5-2-00 Mr. Hardegree advised that he had gotten statement under oath from Ms.

Hollis on 4-20-00. Insurance company has offered to settle with her for

$27,000, the cost of repair, but Ms. Hollis wants $47,000, which is the limit

the insurance company will pay. Extended to 7-1-00

Mr. Patrick is not representing Ms. Hollis, Hillman Toombs is new

attorney.



7-11-00 Per Mr. Hardegree, Ms. Hollis will not accept offer from insurance

company. She wants more money, however; Southern Mutual sent her a check for

$26,900. Per Martin Wells at insurance company, Ms. Hollis was sent a letter

with mediator offers (insurance will pay her more if insurance company adjuster

and Ms. Hollis ' adjuster and mediator agree that loss was more than $27,000).

Ms. Hollis has not responded to offer.

Per Cathy Morgan, 1st Union Bank, she did not know that Ms. Hollis had

been sent a check.





CHRONOLOGY

Page 3

March 4, 2003



8-16-00 Housing Code Coordinator talked with Cathy Morgan, 1st Union Bank, the

insurance company cancelled insurance on this property in July. Ms. Hollis did

not get any more insurance, so 1st Union is calling their loan due. Demolition

process will proceed.



10-23-00 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for approval

of demolition.



10-23-00 Requested asbestos survey from GLE Associates.



11-17-00 Received asbestos survey from GLE Associates.



12-7-00 Craig Reaves, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $9,930.00 and GLE Associates priced the cost of

asbestos survey at $409.00, totaling $10,339.00.



12-13-00 Mr. Hardegree advised that insurance company will send another check.

(Ms. Hollis did not cash, so they stopped payment.)



1-12-01 Received letter from Ms. Hollis advising that she had not settled with

insurance company .



1-30-01 Letter mailed to owner requesting an appointment to meet an inspector

on site. No response received from Ms. Hollis.



7-20-01 Notice sent to owner providing a list of minimum requirements to bring

property in compliance with the applicable codes.



8-29-01 Inspections revealed that house is boarded up. We will extend to see

if Ms. Hollis repairs.



1-22-03 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for first

reading. (It has now been two (2) years since Ms. Hollis received insurance

payment. No repairs have been made.)



2-5-03 Received letter from Ms. Hollis.



2-26-03 Re-inspections and new photographs revealed that no progress has been

made.



CHRONOLOGY

Page 4

March 4, 2003



2-27-03 Letter mailed to owner advising the cost of demolition and Council

dates.



3-11-03 Ordinance providing for demolition goes to Council for first reading.







STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: JACKSON, Ulysses &

Life Estate of Everlena Mitchell



ADDRESS: 6747 Mitchell Drive



DATE: March 4, 2003



I: LOCATION: Tax Map 113, Block 14, Lot 24



II: BUILDING CONDITION AND CURRENT STATUS:



At the time original inspection was made, structure was 30% - 60%

rotten. Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



10-30-00 Biggers Construction Company bought permit to add master bedroom, bath

and kitchen to rear of house. Work was not completed and permit was expired

July, 2002.



1-31-01 Manners Electric bought electric permit for a change of service and

additional wiring. Permit was expired March , 2002.



5-15-02 Ms. Lightfoot bought building & plumbing permits. No work was done and

no inspections were called for.



(All of this occurred prior to condemnation)



10-15-02 Housing Code Inspector inspected the property, and found the structure

to be rotten and unsafe, made photographs of the structure, and wrote up

"Inspector's Condemnation Report".



11-13-02 Notice of hearing to be held mailed to owner of record.



11-27-02 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed to

owner.



1-14-03 Inspections revealed that no progress has been made.



1-22-03 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for approval

of demolition.



1-22-03 Requested asbestos survey from GLE Associates.



CHRONOLOGY

Page 2

March 4, 2003



2-21-03 Received asbestos survey from GLE Associates.



2-26-03 Scott Cawley, Reaves Wrecking Company, Inc., price the cost of

completing the demolition at $2,897.50 and GLE Associates priced the cost of

asbestos survey at $325.00 totaling $3,222.50.



2-26-03 Re-inspections and new photographs revealed that no progress has been

made.



2-27-03 Letter mailed to owner advising demolition costs and Council dates.



3-11-03 Ordinance providing for demolition goes to Council for first reading.





STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: JAMES, Agnes



ADDRESS: 336 Clover Avenue, Rear



DATE: March 4, 2003



I: LOCATION: Tax Map 64, Block 01, Lot 21



II: BUILDING CONDITION AND CURRENT STATUS:



At the time original inspections were done, structure was 15% - 100%

dilapidated. Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



9-27-02 Housing Code Inspector inspected properties, and found the structure to

be dilapidated, made photographs of the structure, and wrote up "Inspector's

Condemnation Report".



10-9-02 Notice of hearing to be held mailed to owner of record.



10-23-02 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed to

owner.



11-8-02 Owner's granddaughter bought permit to repair.



12-12-02 Inspections revealed unlicensed people doing work. Work did not meet

code. Permit voided.



1-22-03 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from price from Reaves Wrecking, and send to Council

for approval of demolition.



1-22-03 Requested asbestos survey from GLE Associates.



1-28-03 Tri-State bought permit to repair soffett & fascia only.



2-21-03 Received asbestos survey from GLE Associates.



2-26-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $3,271.50 and GLE Associates priced the cost of

asbestos survey at $325.00 totaling $3,596.50.



2-26-03 Re-inspections and new photographs revealed that no additional progress

has been made.

CHRONOLOGY

Page 2

March 4, 2003





2-27-03 Letter mailed to owner advising cost of demolition and Council dates.



3-11-03 Ordinance providing for demolition goes to Council for first reading.







STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: JORDAN, W. Richard, Jr.



ADDRESS: 1415 - 29th Street



DATE: March 4, 2003



I: LOCATION: Tax Map 29, Block 21, Lot 08



II: BUILDING CONDITION AND CURRENT STATUS:



At the time original inspection was made, property was 30% - 80% dilapidated.

Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



6-27-02 Housing Code Inspector inspected the property, and found the structure

to be dilapidated, made photographs of the structure, and wrote up "Inspector's

Condemnation Report".



7-10-02 Notice of hearing to be held mailed to owner of record.



7-24-02 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed to

owner.



9-9-02 Inspections revealed that no progress has been made, sprayed red D.



10-10-02 Owner bought permit to repair. Tore off siding and porch, no other

progress. Has not called for any inspections.



1-22-03 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for approval

of demolition.



1-22-03 Requested asbestos survey from GLE Associates.



2-21-03 Received asbestos survey from GLE Associates.



2-26-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $2,144.20 and GLE Associates priced the cost of

asbestos survey at $325.00 totaling $2,469.20.



2-26-03 Re-inspections and new photographs revealed that no progress has bee

made.



2-27-03 Letter mailed to owner advising the cost of demolition and Council

dates.

CHRONOLOGY

Page 2

March 4, 2003



3-11-03 Ordinance providing for demolition goes to Council for first reading.







STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: ROBERSON, Jonnie Lee, Estate



ADDRESS: 621 Radcliff Avenue



DATE: March 4, 2003



I: LOCATION: Tax Map 50, Block 41, Lot 10



II: BUILDING CONDITION AND CURRENT STATUS:



At the time original inspection was made, structure was 50% - 100% burned.

Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



12-11-01 Housing Code Inspector inspected the property, and found the structure

to be burned, made photographs of the property, and wrote up "Inspector's

Condemnation Report".



1-9-02 Notice of hearing to be held mailed to owner of record.



1-23-02 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed to

owner.



1-23-02 Ran legal ad.



3-22-02 Housing Code Coordinator spoke with Attorney Mary Buckner, who is

handling estate of deceased owner. Ms. Buckner advised that she has done all

paperwork to make owners granddaughter executrix of estate. Insurance company

is ready to settle to repair house.



7-30-02 Executrix has not taken oath from probate court to be able to handle

estate.



8-27-02 Attorney Mary Buckner called and advised that granddaughter had taken

oath as executrix of estate.



10-30-02 Granddaughter has been appointed executrix of estate and insurance

company has settled. No progress has been made.



1-22-03 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for approval

of demolition.



1-22-03 Requested asbestos survey from GLE Associates.



CHRONOLOGY

Page 2

March 4, 2003



2-21-03 Received asbestos survey from GLE Associates.



2-26-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $2,992.50 and GLE Associates priced the cost of

asbestos survey at $325.00 totaling $3,317.50.



2-26-03 Re-inspections and new photographs revealed that no progress has been

made.



2-27-03 Letter mailed to owner advising cost of demolition and Council dates.



3-11-03 Ordinance providing for demolition goes to Council for first reading.





STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: RYDER, Carolyn E. & Orlando



ADDRESS: 44 & 46 Muscogee Drive



DATE: March 4, 2003



I: LOCATION: Tax Map 63, Block 46, Lot 03



II: BUILDING CONDITION AND CURRENT STATUS:



At the time original inspection was made, structures were 40% - 100% vandalized

and neglected. Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



9-5-02 Housing Code Inspector inspected the properties, and found the

structures to be vandalized and neglected, made photographs of the structures,

and wrote up "Inspector's Condemnation Report".



10-9-02 Notice of hearing to be held mailed to owner of record.



10-23-02 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed to

owner.



12-12-02 Inspections revealed that no progress has been made, sprayed red D.



1-22-03 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for approval

of demolition.



1-22-03 Requested asbestos survey from GLE Associates.



2-21-03 Received asbestos survey from GLE Associates.



2-26-03 Scott Cawley, Reaves Wrecking Company, Inc. priced the cost of

completing the demolition at $4,705.25 and GLE Associates priced the cost of

asbestos survey at $332.00 totaling $5,037.25.



2-26-03 Re-inspections and new photographs revealed that no progress has been

made.



2-27-03 Letter mailed to owner advising the cost of demolition and Council

dates.



3-11-03 Ordinance providing for demolition goes to Council for first reading.





STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: TEW, Katie B.



ADDRESS: 2004 - 3rd Avenue



DATE: March 4, 2003



I: LOCATION: Tax Map 06, Block 10, Lot 04



II: BUILDING CONDITION AND CURRENT STATUS:



At the time original inspection was made, structure was 30% - 100%

dilapidated. Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



10-8-02 Housing Code Inspector inspected the property, and found the structure

to be dilapidated and rotten, made photographs of the structure, and wrote up

"Inspector's Condemnation Report".



11-13-02 Notice of hearing to be held mailed to owner of record.



11-27-02 Hearing held. Forty-five day "Notice to Repair or Demolish" delivered

to owner.



1-14-03 Inspections revealed that no progress has been made, sprayed red D.



1-22-03 Letter mailed to owner that we were requesting asbestos survey, after

which we would get price from Reaves Wrecking, and send to Council for approval

of demolition.



1-22-03 Requested asbestos survey from GLE Associates.



2-21-03 Received asbestos survey from GLE Associates.



2-26-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $10,334.80 and GLE Associates priced the cost of

asbestos survey at $346.00 totaling $10,680.80.



2-26-03 Re-inspections and new photographs revealed that no progress has been

made.



2-27-03 Letter mailed to owner advising cost of demolition and Council dates.



3-11-03 Ordinance providing for demolition goes to Council for first reading.

STATUS & CHRONOLOGY OF PROPERTY UNDER DEMOLITION NOTICE



OWNER: U.S. BANK NATIONAL ASSOCIATION



ADDRESS: 3042 Knox Street, 1 & 2



DATE: March 4, 2003



I: LOCATION: Tax Map 59, Block 31, Lot 20



II: BUILDING CONDITION AND CURRENT STATUS:



At the time original inspection was made, accessory structures were

dilapidated. Owner has done nothing either to repair or demolish.



III: CHRONOLOGY



10-9-02 Housing Code Inspector inspected the properties, and found the

accessory structures to be dilapidated, made photographs of the structures, and

wrote up "Inspector's Condemnation Report".



11-13-02 Notice of hearing to be held mailed to owner of record.



11-27-02 Hearing held. Forty-five day "Notice to Repair or Demolish" mailed to

owner.



1-14-03 Inspections revealed that no progress has been made, sprayed red D.



1-22-03 Letter mailed to owner that we were requesting asbestos survey, after,

which we would get price from Reaves Wrecking, and send to Council for approval

of demolition.



1-22-03 Requested asbestos survey from GLE Associates.



2-21-03 Received asbestos survey from GLE Associates.



2-26-03 Scott Cawley, Reaves Wrecking Company, Inc., priced the cost of

completing the demolition at $1,220.00 and GLE Associates priced the cost of

asbestos survey at $325.00 totaling $1,545.00.



2-26-03 Re-inspections and new photographs revealed that no progress has been

made.



2-27-03 Letter mailed to owner advising the cost of demolition and Council

dates.



3-11-03 Ordinance providing for demolition goes to Council for first reading.