To
-
Mayor and Council
-
Subject
-
Street Acceptance - Turnberry Lane and Wailea Court
-
Initiator
-
Engineering Department
-
Recommendation
-
Approve the acceptance of the deed to Turnberry Lane and Wailea Court located \n \n in Section "L" - Phase II, Maple Ridge Golf Community.
-
Approval
-
Approved
-
Background
-
Section "L" - Phase II, Maple Ridge Golf Community, has 21 residential
lots. The streets have been improved and meet the required specifications for
acceptance by the city.
-
Analysis
-
A deed has been conveyed to the City conveying Turnberry Lane and Wailea Court
located in Section "L" - Phase II, Maple Ridge Golf Community. A description
of the property is as follows: "All those tracts and parcels of land situate,
lying and being in the State of Georgia, County of Muscogee, and City of
Columbus, and being known and designated as shown on that certain map or plat
entitled "Section "L" - Phase II, Maple Ridge Golf Community, Part of Land Lot
268, 19th District, Columbus, Muscogee County, Georgia" dated June 30, 2003,
made by Moon, Meeks, Mason & Vinson, Inc., and recorded in Plat Book 149, Folio
40, of the records in the Office of the clerk of the Superior Court of Muscogee
County Georgia, to which plat reference is hereby made for more specific
dimensions, as the following herein described streets, to-wit:" All of Wailea
Court and Turnberry Lane, including those portions adjacent to Veterans Parkway
for an acceleration and deceleration lane, as shown on said map or plat.
-
Financial Considerations
-
No City funds are involved until maintenance is assumed after the two-year
warranty expires.
-
Projected Annual Fiscal Impact Statement
-
-
Legal Considerations
-
In accordance with Section 18-3 of the Columbus Code, all dedicated
right-of-ways must be accepted by written resolution of Council.
-
Recommendations/ Actions
-
Approve the Resolution accepting a deed to Turnberry Lane and Wailea Court
located in Section "L" - Phase II, Maple Ridge Golf Community.