To
-
Mayor and Council
-
Subject
-
Green Island Drive - Permanent Street Closure
-
Initiator
-
Engineering
-
Recommendation
-
Approve the permanent street closure and disposal of Green Island Drive \n \n beginning at a newly constructed cul-de-sac at Gaines Creek Road northeasterly \n \n to the west right-of-way of River Road
-
Approval
-
Approved
-
Background
-
Columbus Regional Senior Living, Inc., is in the process of developing a
Continuing Care Retirement Community on 40 acres of property between River Road
and Green Island Drive. The project is scheduled to have 196 Apartment Homes
and Garden Villas
The total cost of construction will exceed $54 million and when fully occupied
will have an annual operation budget in excess of $10 million. The facility
will employ nearly 200 full and part-time staff members.
During the planning and development phase of the project, a request was made by
the Developer to the close off Green Island Drive from the entrance of Gaines
Creek to River Road. A number of Public Meetings were held with the Home
Owners Association of Gaines Creek and the adjacent property owners.
An agreement has been reached that satisfies the Gaines Creek Homeowners
Association, adjacent property owners and City Staff. A Resolution authorizing
the disposal of this street segment will be on the Council Agenda with the 2nd
reading of this ordinance.
-
Analysis
-
An agreement has been reached that satisfies the Gaines Creek Homeowners
Association, adjacent property owners and City. As part of this process, Green
Island Drive will be cul-de-saced at Gaines Creek Road.
-
Financial Considerations
-
The value of this street and right-of-way will be quit claimed to the
developer.
-
Projected Annual Fiscal Impact Statement
-
-
Legal Considerations
-
The closure of Green Island Drive and the disposal of the street and
right-of-way requires Council approval.
-
Recommendations/ Actions
-
Council is requested to approve the attached ordinance for the permanent street
closure and disposal of Green Island Drive beginning at a newly constructed
cul-de-sac at Gaines Creek Road northeasterly to the west right-of-way of River
Road.