Wynnton Road Master Plan - Supplemental Agreement Number 1
Initiator
Planning Department
Recommendation
Approve the resolution authorizing the City Manager to sign the Supplemental \n \n Agreement Number 1, with the Georgia Department of Transportation (GDOT) for \n \n the Wynnton Road Master Plan (streetscapes) project.
Approval
Pending
Background
Resolution No. 338-08 authorized the City Manager to accept funds for the
construction of this streetscapes project along Wynnton Road, from Peacock
Avenue to Hilton Avenue. Since that time construction has begun and is
expected to be completed by fall of this year. The original contract with GDOT
establishes a completion date of no later than December 31, 2018. In order to
insure that the contractural obligations are met under this agreement, GDOT has
requested that a supplement agreement be signed, extending the completion date
to December 31, 2019.
Analysis
Authorizing the City Manager to enter into this agreement will protect the
funding for this project in the event the construction work should go beyond
the original date of December 31, 2018.
Financial Considerations
The agreement will maintain the level of funding now established for this
project.
Projected Annual Fiscal Impact Statement
There will not be any additional fiscal impact under this agreement.
Legal Considerations
The City Attorney has approved this agreement.
Recommendations/ Actions
Approve the resolution authorizing the City Manager to sign the Supplemental
Agreement Number 1, with the Georgia Department of Transportation (GDOT) for
the Wynnton Road Master Plan (streetscapes) project.