To
-
Mayor and Council
-
Subject
-
Acceptance of Detention Basin located in Third Addition to Whitesville Walk
-
Initiator
-
Engineering
-
Recommendation
-
Approve the acceptance of the deed to the Detention Basin located in Third \n \n Addition to Whitesville Walk.
-
Approval
-
Pending
-
Background
-
The Detention Basin was constructed for Third Addition to Whitesville Walk and
is 1.11 Acres. The owner has maintained the pond since construction for the
period of at least two (2) years.
-
Analysis
-
A deed has been submitted conveying to the City of Columbus a detention basin
located in the Third Addition to Whitesville Walk. Description of property is
as follows: All that lot, tract and parcel of land situate, lying and being in
the State of Georgia, County of Muscogee and City of Columbus, and being shown
as "Detention Basin, 1.11 AC." on that certain map or plat entitled "Third
Addition to Whitesville Walk, Lying in Land Lots 62, & 70, 8th District,
Columbus, Muscogee County, Georgia" prepared by Moon, Meeks, Mason and Vinson,
Inc., under date of February 23, 2011, a copy of same being recorded in Plat
Book 163, Folio 21, of the records in the Office of the Clerk of Superior Court
of Muscogee County Georgia.
-
Financial Considerations
-
The owner has maintained the basin since its construction for the period of at
least 2 years therefore the City will be responsible for maintaining the
Detention Basin, 1.11 Acres, located in Third Addition to Whitesville Walk.
-
Projected Annual Fiscal Impact Statement
-
The Public Works Department will be responsible for maintaining the Detention
Basin after acceptance by the City.
-
Legal Considerations
-
In accordance with Section 18-3 of the Columbus Code, all dedicated
right-of-ways must be accepted by Council.
-
Recommendations/ Actions
-
Approve the Resolution accepting a deed to the Detention Basin, 1.11 Acres,
located in Third Addition to Whitesville Walk.
No attachments for this document.