To
-
Mayor and Council
-
Subject
-
Cherokee Avenue - Re-striping and Safety Improvements
-
Initiator
-
Engineering Department
-
Recommendation
-
Approval is requested to authorize the re-striping of Cherokee Avenue as a \n \n four-lane roadway with traffic safety improvements.
-
Approval
-
Approved
-
Background
-
Cherokee Avenue has been studied to provide traffic safety improvements from
Garrard Street north to Camille Avenue to reduce the potential for traffic
accidents with vehicles ending up in Weracoba Creek. Traffic safety
improvements were considered to include channelizing the creek, installing
guardrail, installing a three-lane section with reversible lanes, re-striping
as a three-lane section with a clear zone buffer next to the creek to
continuing the roadway as a four-lane roadway.
-
Analysis
-
During this evaluation period, a public information hearing was held to include
considerable discussion involving the pros and cons of various alternatives.
Concurrently, with the discussion period, there has been significant utility
work that limited the use of all lanes during construction. The construction
projects are nearing completion with asphalt resurfacing ready to begin.
Knowing that the 2007 school year begins the second week of August, it is
important to place this street back into operation prior to opening day of
school. To accomplish this goal, the City Manager recommends re-striping
Cherokee Avenue as a four-lane roadway with certain interim traffic safety
improvements. These improvements include the reconfiguration of the Camille
Avenue at Cherokee Avenue (completed), install rumble strips at key locations
to alert motorists of roadway curvature and install a flashing light at or near
the Cherokee Avenue and Slade Drive intersection. A critical component of
these safety improvements will be a concentrated and cooperative speed
enforcement of this section of Cherokee Avenue with zero tolerance to
speeding. The speed enforcement will be provided using all of the City's
Public Safety Departments.
-
Financial Considerations
-
The re-striping and safety improvements will be implemented thru the Traffic
Engineering Division Operating budget in an amount estimated from $7,500 to
$8,500.
-
Projected Annual Fiscal Impact Statement
-
-
Legal Considerations
-
This action is being supported by a resolution approved by Council.
-
Recommendations/ Actions
-
Approved the attached resolution authorizing the re-straining of Cherokee
Avenue as a four-lane roadway with traffic safety improvements.
No attachments for this document.