To
-
Mayor and Council
-
Subject
-
Project Framework Agreement for Transportation High Priority Projects
-
Initiator
-
Planning Department
-
Recommendation
-
Approval is requested to enter into a Project Framework Agreement (PFA) for the \n \n following Georgia Department of Transportation High Priority Projects: \n \n Streetscapes in Columbus Phase III (Riverwalk); Trolley Trail and Bike Path, \n \n and South Lumpkin Road Trail.
-
Approval
-
Approved
-
Background
-
The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy
for Users (SAFETEA-LU) was enacted August 10, 2005, by Congress, which includes
projects that are identified as "High Priority Projects." The local
Congressional delegation sponsored the following projects for Columbus:
Streetscapes in Columbus Phase III (Riverwalk) CSSTP-0007-00 (559) - $1
million; Trolley Trail and Bike Path CSSTP-0007-00 (563) - $500,000; and the
South Lumpkin Road Trail CSSTP-0007-00 (559) - $500,000.
-
Analysis
-
The projects are federally funded through the administration of the Georgia
Department of Transportation. The funds will be used to help leverage existing
construction activities for the Riverwalk, and the proposed rails to trails
projects. Construction funding from these grants will be made available for
the Riverwalk section in FY07 and for the trail and bike paths in FY09.
-
Financial Considerations
-
Funding for these projects will require a twenty (20) percent match:
Streetscapes in Columbus Phase III (Riverwalk) CSSTP-0007-00 (559) - $200,000;
Trolley Trail and Bike Path CSSTP-0007-00 (563) - $100,000; and the South
Lumpkin Road Trail CSSTP-0007-00 (559) - $100,000. Funding for this match have
been identified from City SPLOST and Capital Improvement Projects.
-
Projected Annual Fiscal Impact Statement
-
-
Legal Considerations
-
The City will be required to adhere to all legal requirements as established by
the GDOT.
-
Recommendations/ Actions
-
Authorize the City Manager to sign the Project Framework Agreement (PFA) for
the following Georgia Department of Transportation High Priority Projects:
Streetscapes in Columbus Phase III (Riverwalk); Trolley Trail and Bike Path,
and South Lumpkin Road Trail.
No attachments for this document.